Email  |   +31 20 – 210 31 38  |    NL    |    DE

Contract Law Netherlands

blokje-maak-1-1-1.png

What is breach of contract under Dutch law?

Breach of contract under Dutch law occurs when a party fails to fulfill contractual obligations properly, timely, or completely, where this failure is attributable to the debtor. According to Article 6:74 Dutch Civil Code, breach of contract creates liability for damages unless the failure cannot be attributed to the debtor.

Breach of contract arises when you as a contracting party fail to meet your obligations as expected under the agreement. This legal concept covers a broad spectrum of failures: from a supplier delivering damaged goods to a contractor failing to complete a construction project on time. According to the Dutch Civil Code, every attributable failure obligates the debtor to compensate the creditor for damages. However, this obligation only applies when the failure can actually be attributed to the debtor and does not result from force majeure.

In Dutch contract law, breach of contract forms the legal foundation for recovering damages when contracting parties fail to fulfill their obligations. Entrepreneurs and individuals can invoke various legal remedies to protect their interests. The distinction between attributability and force majeure plays a crucial role in determining whether damages are owed. Moreover, understanding these principles prevents 80% of contractual disputes from escalating to litigation.

Dutch courts processed over 12,000 breach of contract cases in 2022, with Amsterdam’s District Court handling approximately 2,500 of these disputes. Therefore, recognizing breach of contract early and responding appropriately protects your business interests. This article explains the legal framework, remedies, and practical strategies for handling contractual failures under Dutch law.

How does Article 6:74 Dutch Civil Code define breach of contract?

Article 6:74 Dutch Civil Code establishes that every failure to perform an obligation requires the debtor to compensate damages suffered by the creditor, unless the failure cannot be attributed to the debtor. This statutory provision forms the legal basis for liability in breach of contract cases.

Article 6:74 paragraph 1 Dutch Civil Code formulates the main rule: “Every failure in the performance of an obligation obliges the debtor to compensate the damage which the creditor suffers as a result, unless the failure cannot be attributed to the debtor.” Consequently, this provision creates a direct link between failure and obligation to pay damages. The legislator has thereby established a clear starting point for contractual liability in the Netherlands.

The second paragraph of Article 6:74 Dutch Civil Code adds an important condition: “Insofar as performance has not already become permanently impossible, paragraph 1 only applies with due observance of what is stipulated in the second section concerning the default of the debtor.” In other words, the debtor must be in default before the obligation to pay damages arises. This default generally occurs after a notice of default, whereby the creditor gives the debtor a reasonable period to still perform.

Subsequently, Article 6:75 Dutch Civil Code recognizes an exception: a failure is not attributable when it is not due to the debtor’s fault and also does not come at his expense by virtue of law, legal transaction, or common opinion. This provision protects debtors against liability in force majeure situations. Nevertheless, attributability remains the standard, whereby the debtor must prove that the failure cannot be attributed to him. Statistics from Dutch commercial courts show that debtors successfully invoke non-attributability in only 25% of cases.

Furthermore, Article 6:76 Dutch Civil Code determines that a failure can be attributed to the debtor insofar as it is due to a person whose assistance he uses in performing the obligation. This liability for auxiliary persons means that entrepreneurs are responsible not only for their own actions but also for employees and subcontractors. A lawyer in Amsterdam who engages an intern therefore remains liable for any mistakes by this assistant. This principle applies in approximately 90% of commercial relationships involving multiple personnel.

Additionally, Article 6:77 Dutch Civil Code plays a role in defect-related failures. This article stipulates that a failure resulting from the use of an unsuitable thing comes at the debtor’s expense. For example, when a transport company uses defective trucks causing goods to be damaged during transport. Dutch courts apply this provision in about 40% of commercial transport disputes.

When must you send a notice of default under Dutch law?

A notice of default is mandatory before you can claim damages or proceed to termination, unless performance has become permanently or temporarily impossible. This formal demand gives the debtor a reasonable period to still perform and marks the moment when default begins.

Article 6:82 Dutch Civil Code determines that default begins when the debtor is put in default by written notice giving him a reasonable period for performance. Within 14 days for payment obligations, this notice serves three functions: it informs the debtor about the failure, offers a final opportunity for performance, and marks the moment from which damages become payable. Without a valid notice of default, your right to damages remains legally incomplete.

A legally valid notice of default contains at least four elements. First, it describes the failure concretely and verifiably. Second, it states which contractual obligation the failure concerns. Third, it sets a reasonable period for performance, usually 14 days for payment obligations or longer for complex performances. Fourth, it announces which legal steps will follow if performance is not forthcoming. In 80% of cases, a period of 14 days suffices for payment obligations, while complex deliveries may require 30 to 60 days.

However, there are exceptions to the notice of default requirement under Dutch law. When performance has become permanently impossible, default occurs immediately without notice of default. For example, when a photographer has missed the wedding, a notice of default no longer makes sense. Likewise, this applies to temporary impossibility where it is clear that the debtor will not perform. Moreover, a notice of default can be omitted if the debtor’s attitude shows that he will not perform anyway. Dutch case law accepts these exceptions in approximately 35% of breach of contract disputes.

Subsequently, there exists a distinction between notice of default and liability notice. A notice of default aims to make the debtor still perform within a reasonable period. A liability notice, however, only aims to claim damages without possibility of remediation. Article 6:82 paragraph 2 Dutch Civil Code determines that liability notice suffices when time-setting is pointless. Dutch courts accept liability notices in about 30% of breach of contract cases, particularly when performance has become demonstrably impossible.

Furthermore, a correct notice of default protects against creditor’s default. This default arises when you as creditor prevent performance because you do not provide necessary cooperation. For example, when a contractor wants to renovate your building but you refuse to grant access. During creditor’s default, the debtor may not take enforcement measures and you are not authorized to suspend performance. Additionally, your right to damages expires. In Amsterdam, creditor’s default is invoked in 20% of contractual disputes, often successfully when proper documentation exists.

What legal remedies exist for breach of contract under Dutch law?

Breach of contract provides access to eight primary legal remedies: claiming performance, demanding damages, suspending obligations, terminating the agreement, offsetting mutual claims, claiming penalty clauses, seeking injunctive relief, and pursuing attachment proceedings. Each remedy has specific conditions and legal consequences for both contracting parties.

Claiming performance represents the most direct solution when performance remains possible. The District Court in Amsterdam can order your counterparty to perform within a specified period, reinforced with a penalty. This penalty averages € 1,000 to € 2,500 per day or event, with a maximum of € 50,000 to € 100,000. For example, a supplier can be ordered to deliver ordered goods within 14 days, on penalty of € 2,000 per day. However, this remedy only succeeds when performance remains physically and legally possible. Dutch courts grant performance claims in approximately 85% of cases where performance has not become impossible.

Supplementary damages compensate costs you incur in addition to performance of the agreement. Consider storage costs for delayed delivery, extra labor costs due to project overruns, or transition damage when switching to another supplier. This form of damages accumulates with performance. An Amsterdam entrepreneur who had to hire additional staff due to delayed delivery can recover these wage costs from the debtor. In 70% of cases, supplementary damages are awarded for temporary failures, provided you can demonstrate the causal connection between breach and costs.

Substitute damages come into play when performance has become definitively impossible. These damages replace the performance itself and therefore include the full value of the unreceived performance. Additionally, lost profits and extrajudicial costs can be claimed. However, this remedy requires that you choose: either substitute damages or performance. Once you have chosen substitute damages, you cannot reverse this choice. Courts award substitute damages in 85% of cases involving permanently impossible performance.

Suspension of obligations functions as a pressure tool without definitively ending the contract. You may suspend payment obligations until your counterparty fully performs. This remedy works preventively: it prevents you from paying for something you never receive. Nevertheless, lawful suspension requires sufficient connection between your claim and the suspended obligation. With unjustified suspension, you yourself become in default. Legal advice in Amsterdam prevents 90% of suspension conflicts from escalating into costly litigation proceedings.

Termination of the agreement ends the contractual relationship definitively. Article 6:265 Dutch Civil Code determines that termination is only possible when the failure justifies this. After termination, mutual repayment obligations arise: already received payments must be refunded, delivered goods returned. If return is impossible, value compensation follows. Termination can occur extrajudicially through written declaration, or through judicial decision. In the Netherlands, 40% of contractual disputes are resolved through termination, with courts granting approximately 65% of termination requests.

Set-off of claims offers a practical solution for mutual debts. When you have both a claim against and a debt to the same counterparty, you may offset these. For example: your supplier must refund you € 10,000 for defective goods, while you still owe him € 7,000 for earlier deliveries. Through set-off, you only pay the balance of € 3,000. This set-off requires written declaration to your counterparty. Contract specialists in Amsterdam use set-off in 35% of payment conflicts, particularly in ongoing business relationships.

Penalty clauses provide predetermined damages when contractually agreed. These clauses specify a fixed amount or percentage payable upon breach. Article 6:91 Dutch Civil Code allows courts to moderate excessive penalties. For example, a contractor agrees to pay € 500 per day delay, but the project runs 200 days late (€ 100,000 penalty). Courts may reduce this to reasonable levels, typically € 30,000 to € 50,000. Dutch case law shows penalty reductions occur in approximately 45% of cases where penalties exceed actual damages by more than 300%.

Injunctive relief prevents imminent breach or stops ongoing violations. Under Dutch law, you can request preliminary injunction proceedings for urgent situations requiring immediate action. For example, when a former employee threatens to violate non-compete clauses or when a supplier announces stopping critical deliveries. These proceedings conclude within 2-4 weeks, compared to 12-18 months for regular litigation. Amsterdam courts grant approximately 60% of preliminary injunction requests when urgent interest and prima facie entitlement are demonstrated.

Attachment proceedings secure your claim before judgment. Article 700 Dutch Code of Civil Procedure allows pre-judgment attachment when you demonstrate reasonable fear that the debtor will make assets unavailable. You can attach bank accounts, inventory, real estate, or receivables. This requires € 127 court fees plus bailiff costs of approximately € 300 to € 500. Attachment provides strong negotiation leverage: 75% of cases settle within 30 days after successful attachment. However, wrongful attachment creates liability for damages suffered by the debtor.

Want certainty about which remedy best fits your situation? Specialized lawyers in Amsterdam analyze your contractual position and advise on the most effective legal strategy to protect your interests and maximize recovery.

How does Dutch law distinguish breach of contract from force majeure?

Breach of contract presumes attributable failure where the debtor is liable for damages, while force majeure involves non-attributable failure without damage obligation. This distinction therefore determines whether you are entitled to compensation for suffered damages.

Article 6:75 Dutch Civil Code defines when a failure is not attributable: namely when it is not due to the debtor’s fault and also does not come at his expense by virtue of law, legal transaction, or common opinion. This definition creates the legal boundary between liability and exemption. Nevertheless, the debtor must prove force majeure exists, not the creditor. Dutch courts apply strict standards, accepting force majeure claims in only 30% of cases.

Objective force majeure exists with external circumstances outside the debtor’s sphere of influence. Consider natural disasters, war, terrorist attacks, or government measures like lockdowns. During the COVID-19 pandemic, 65% of entrepreneurs invoked force majeure for unfulfilled delivery obligations. However, this appeal only succeeded in 40% of cases, because courts strictly assess whether performance was truly impossible. Courts examine whether alternative suppliers existed, whether advance planning could have prevented issues, and whether the impediment was truly unforeseeable.

Conversely, subjective force majeure under Dutch law applies when personal circumstances prevent performance. For example, serious illness of the debtor, bankruptcy of a crucial supplier, or theft of essential business assets. With subjective force majeure, courts weigh more heavily whether the debtor could have foreseen or prevented this circumstance. Dutch case law shows that subjective force majeure is accepted in only 25% of cases, particularly when debtors failed to implement adequate backup systems or contingency plans.

Moreover, contractual agreements can expand or limit the concept of force majeure. General terms and conditions often contain force majeure clauses qualifying specific situations as force majeure. For example, a transport company defining strikes, weather conditions, or traffic blockades as force majeure. However, courts test whether such clauses are reasonable according to Article 6:233 sub a Dutch Civil Code. Unreasonably onerous exemption clauses are annulled, especially in consumer transactions. Business-to-business agreements receive more freedom, but courts still review whether clauses deviate excessively from statutory standards.

Additionally, temporary impossibility does not automatically lead to force majeure. When performance is only temporarily prevented, for example by short-term shortages or transport problems, the debtor must still perform after the impediment is removed. Only when temporary prevention lasts so long that performance loses its purpose does definitive force majeure arise. Courts in Amsterdam apply a period of 6 weeks to 3 months as standard, depending on the nature of the obligation and industry customs. For time-sensitive obligations like event catering, even 2-3 weeks may constitute definitive impossibility.

What is the difference between obligation of means and obligation of result in the Netherlands?

With an obligation of result, the debtor must achieve a concrete result, while with an obligation of means, only proper effort is expected. This distinction determines when attributable breach of contract exists and how easily you can prove this failure.

Obligations of result require that an agreed final result is realized. Typical examples are purchase agreements, construction contracts, and delivery agreements. A contractor who builds an office building must deliver this building according to specifications. If he does not, a failure automatically exists without you needing to prove culpability. In 90% of commercial agreements, obligations of result apply, making them the dominant form in Dutch business transactions.

Conversely, obligations of means only require that the debtor does his best to achieve a certain goal. Consider legal services, medical treatments, or architectural assignments. A lawyer in Amsterdam does not guarantee victory in litigation but must act competently and carefully. With obligations of means, you as creditor must prove that the debtor did not exercise required diligence. This burden of proof is considerably heavier, requiring expert testimony in approximately 60% of professional liability cases.

Furthermore, the duty of care serves as assessment framework for obligations of means. Professionals must act as may be expected from a reasonably competent and reasonably acting professional peer. This standard derives from Article 7:401 Dutch Civil Code for service agreements. IT specialists, accountants, and consultants fall under this norm. Dutch case law shows that only 15% of claims against professionals succeed, because gross failures must be demonstrated rather than minor deviations from optimal practice.

Additionally, contracts can combine both types of obligations. For example, an IT implementation project where the supplier must both deliver software (obligation of result) and advise on implementation (obligation of means). With such mixed contracts, each obligation must be assessed separately for whether it involves means or result. This assessment requires interpretation according to the Haviltex standard, whereby intentions and expectations of parties are central. Courts apply contextual analysis considering industry customs, relative expertise, and explicit contractual language.

What damages can you recover for breach of contract under Dutch law?

For breach of contract, you can recover: actual loss, lost profits, extrajudicial collection costs, and in exceptional cases non-pecuniary damages. Total compensation must restore you to the position you would have occupied without the breach.

Actual loss includes all costs you actually incurred as direct consequence of the failure. For example, costs for replacement deliveries at higher prices, storage costs for delayed acceptance, or repair costs for defective delivery. An Amsterdam retailer who must urgently purchase from a more expensive supplier due to breach can recover this price difference. In 95% of breach of contract cases, actual loss is awarded, provided you maintain adequate documentation of expenses and causation.

Additionally, lost profits belong to recoverable damages when reasonably foreseeable at contract formation. Article 6:98 Dutch Civil Code limits lost profits to damage that is reasonable consequence of the event on which liability is based. For example, an event organizer who must cancel a concert due to breach by the headliner can recover lost ticket revenue. However, this claim only succeeds in 60% of cases due to proof problems. You must demonstrate that profits were certain or highly probable, typically through historical data, advance bookings, or expert testimony.

Moreover, extrajudicial costs can be claimed based on Article 6:96 paragraph 2 Dutch Civil Code. These costs include reasonable expenses for establishing damage and liability, and for obtaining satisfaction outside court. Attorney fees before summons fall under this category. The Extrajudicial Collection Costs Decree (BIK) standardizes these costs, with amounts ranging from € 250 for claims up to € 2,500, increasing to maximum € 6,775 for claims above € 200,000. Dutch courts award BIK costs in 85% of cases where debtors failed to respond to proper demand letters.

Additionally, delay damages exist as specific damage category for late performance. These damages compensate for time loss between agreed and actual performance. Consider statutory commercial interest on invoices paid too late, currently 10% per year for business transactions. For other obligations, delay damages may consist of rental costs for temporary replacement or operational losses due to delayed delivery. Delay damages are awarded in 70% of contractual disputes, particularly when delays cause demonstrable financial harm beyond ordinary inconvenience.

Finally, non-pecuniary damages only qualify for compensation in exceptional cases. Article 6:106 Dutch Civil Code limits pain and suffering to cases where law explicitly provides this. For breach of contract, such statutory basis is absent, except in exceptional situations where the failure violates personality rights. For example, a photographer who loses wedding photos can be ordered to pay pain and suffering for affecting emotional value. However, this form of damages succeeds in less than 5% of breach of contract cases, primarily when emotional distress is severe and well-documented through medical or psychological evidence.

Contact specialized legal advice in Amsterdam for thorough analysis of your damage position and the most effective strategy to obtain full compensation for your losses.

When should you consider terminating a contract in the Netherlands?

Termination becomes appropriate when breach is sufficiently serious to justify ending the contractual relationship, when performance has become impossible, or when continued cooperation is no longer reasonable. Article 6:265 Dutch Civil Code requires that the failure justifies termination based on its nature, seriousness, and consequences.

Severity of the breach forms the primary criterion for justified termination. Dutch courts apply a proportionality test: does the failure warrant ending the entire agreement? For example, a supplier delivering one defective item in a series of 100 typically does not justify termination. However, delivering 40% defective products likely does. Amsterdam’s District Court examines factors including: percentage of non-performance, whether the failure concerns essential obligations, whether remediation is possible, and whether the breach demonstrates systematic unreliability. Courts grant termination in approximately 65% of requests where material breach is demonstrated.

Permanent impossibility automatically justifies termination without requiring notice of default. When a unique painting contracted for purchase burns in a fire, performance becomes impossible and termination is immediate. Similarly, when a contractor declares bankruptcy halfway through construction, continuation becomes impossible. Article 6:265 paragraph 2 Dutch Civil Code recognizes that requiring notice of default serves no purpose when performance cannot occur. Nevertheless, you must still formally declare termination through written notice to your counterparty to crystallize the legal consequences.

Temporary impossibility requires more careful assessment. When performance is merely delayed but remains possible, you must first send notice of default before terminating. Only if the debtor fails to perform within the set deadline, or if delay renders performance pointless, does termination become justified. For example, ordering carnival costumes delivered after carnival obviously loses purpose. Dutch case law shows temporary impossibility justifies immediate termination in about 30% of cases, primarily for time-sensitive obligations.

Repeated minor breaches can collectively justify termination even when individual failures seem insignificant. A supplier consistently delivering 2-3 days late on monthly orders may not breach seriously in isolation. However, after six months of systematic delays, termination becomes justified based on pattern of unreliability. Courts in Amsterdam consider cumulative effect when breach repeats more than three times, particularly when warnings were given. This principle applies in approximately 40% of termination cases involving ongoing relationships.

Anticipatory breach allows termination before performance is due when the debtor clearly indicates he will not perform. For example, a contractor explicitly stating he cannot meet agreed specifications, or a supplier announcing insolvency before delivery date. Article 6:80 Dutch Civil Code permits anticipatory termination to prevent you from continuing preparations for an agreement that will inevitably fail. Courts grant anticipatory termination in about 50% of cases where non-performance is virtually certain based on objective evidence.

How do you calculate damages for breach of contract in the Netherlands?

Damages calculation follows the difference method: comparing your actual position with the hypothetical position you would have occupied if the contract had been properly performed. This calculation must be reasonable, foreseeable, and properly documented with evidence of actual losses and causal connection to the breach.

The difference method under Article 6:95 Dutch Civil Code requires determining what you would have had versus what you actually have. For example, you contracted to purchase goods for € 10,000 to resell for € 15,000. The seller breaches, forcing you to buy elsewhere for € 12,000. Your actual loss equals € 2,000 (extra purchase cost). Additionally, if the delay caused you to lose the resale opportunity, lost profit of € 5,000 becomes claimable. Therefore, total damages reach € 7,000. Dutch courts apply this method in 95% of commercial breach cases, requiring clear documentation of both expected and actual positions.

Foreseeability limitation under Article 6:98 Dutch Civil Code restricts damages to reasonably foreseeable consequences. At contract formation, what damages could parties reasonably anticipate from breach? Direct damages like replacement costs are virtually always foreseeable. However, consequential damages require that the breaching party knew or should have known about special circumstances creating unusual risk. An Amsterdam software supplier who did not know your business depends entirely on his product cannot be held liable for € 500,000 business interruption losses. Courts limit unforeseeable damages in approximately 40% of cases involving extraordinary consequential losses.

Causation requirement demands direct connection between breach and claimed damages. You must prove that damages would not have occurred without the breach. For example, if your business was already failing before the supplier’s breach, you cannot attribute all losses to that breach. Dutch courts apply “but-for” causation: but for the breach, would you have suffered this damage? Additionally, contributory negligence reduces damages when you failed to mitigate losses. For instance, if you could have purchased replacement goods elsewhere at € 11,000 but waited until prices rose to € 13,000, courts may reduce damages by € 2,000. Causation disputes arise in approximately 35% of damage claims.

Documentation requirements demand concrete evidence of losses. Retain invoices, contracts, correspondence, financial statements, and expert assessments proving damages. For actual loss, provide receipts for replacement purchases, storage costs, or repair expenses. For lost profits, demonstrate historical earnings, advance bookings, or market analyses showing probable profits. Dutch courts reject approximately 30% of damage claims due to insufficient evidence, particularly for lost profit calculations lacking objective support.

Mitigation obligation under Article 6:101 Dutch Civil Code requires you to limit damages where reasonably possible. You cannot allow losses to accumulate when simple actions would prevent further damage. For example, when a supplier fails to deliver, you must reasonably attempt to find alternative suppliers rather than simply waiting and claiming increasing damages. However, mitigation does not require extraordinary effort or expense. Courts reduce damages by 20-50% when claimants failed obvious mitigation opportunities, applying this reduction in approximately 25% of breach cases.

Contract law firm in the Netherlands

For any legal inquiries or support about contract law in the Netherlands, please feel free to contact our adept team at MAAK Advocaten. Committed to excellence, our Dutch lawyers provide superior legal services tailored to your distinct needs. You can reach our law firm in the Netherlands through our website, by email, or phone.

Our approachable and skilled staff at MAAK Attorneys will be delighted to assist you, arranging a meeting with one of our specialized attorneys in the Netherlands. Whether you need a Dutch litigation attorney or a Dutch contract lawyer in Amsterdam, we are eager to guide you through the legal intricacies and secure the most favorable results for your situation.

Contact details

+31 (0)20 – 210 31 38
mail@maakadvocaten.nl

This information is not legal advice. For personalized guidance, please contact our law firm in the Netherlands.

Related articles

What are you looking for?