Under Dutch law, you can end a contract in four ways: by mutual agreement, by notice, by rescission for breach (ontbinding, Article 6:265 DCC) or by annulment (vernietiging) because of a defect when the contract was made. Which route is open to you depends on the contract, the type of agreement and, for long-term contracts, on reasonableness and fairness.
In short
- Rescission under Article 6:265 DCC needs a failure that justifies it and, where performance is still possible, default (usually after a written warning, Articles 6:82 and 6:83).
- Without a notice clause, a long-term contract can in principle be terminated, but reasonableness and fairness (Article 6:248) may require a reason, a notice period or compensation.
- In principle, a client can terminate a services agreement or a construction contract at any time (Articles 7:408 and 7:764); the contractor’s fee is settled afterwards.
- An invalid termination does not end the contract and can leave the sender in breach; have a Dutch lawyer check the route and wording.
This guide is written for foreign businesses whose contract is governed by Dutch law. It explains the general rules in Books 3 and 6 of the Dutch Civil Code (Burgerlijk Wetboek, DCC) and the special rules in Book 7 for services agreements, construction contracts, commercial agency and leases. Employment contracts have separate protective rules that this page does not cover. Dutch statutes have no official English version; the links on this page go to the official Dutch text on wetten.overheid.nl.
Related pages: contract cancellation under Dutch law, early termination of commercial agreements under Dutch law, terminating a franchise agreement under Dutch law, terminating a business agreement under Dutch law, retention of title under Dutch law and sale of drones under Dutch law. For an overview of the field, see Dutch contract law.
How do you terminate a contract under Dutch law?
Dutch law distinguishes between several routes, each with its own requirements and effects. Choosing the wrong route can be costly. A letter that “terminates” a contract with immediate effect may in law be a rescission without the required default, and a notice that is too short can expose you to a claim for damages.
Mutual agreement. The parties can agree to end their contract. They record the end date and the settlement of outstanding obligations in a termination agreement (see below).
Notice (opzegging). A long-term contract (duurovereenkomst) ends for the future by notice from one party. You need a right to give notice under the contract or the law or, for a contract for an indefinite period without a notice clause, under the rules developed by the Dutch Supreme Court (Hoge Raad). A breach by the other party is not required.
Rescission (ontbinding). Every failure in performance gives the other party the right to rescind the contract in whole or in part, unless the failure, given its special nature or minor importance, does not justify rescission with its consequences (Article 6:265(1) DCC). Where performance is not permanently or temporarily impossible, the debtor must first be in default (Article 6:265(2) DCC). Rescission takes place by written statement or by the court (Article 6:267 DCC) and has no retroactive effect, except that an offer to perform made after rescission has been claimed has no effect if the court pronounces the rescission (Article 6:269 DCC).
Annulment (vernietiging). A contract made under mistake, threat, fraud or abuse of circumstances is voidable (Article 6:228 DCC and Article 3:44 DCC). Annulment works retroactively to the moment the contract was made (Article 3:53(1) DCC). Finally, a fixed-term contract normally ends when its term expires, but the law contains exceptions, for example for residential leases (Article 7:271(1) DCC).
Important: A letter is judged by what it does in law, not by its heading. Ending a contract with immediate effect because of a breach is a rescission under Article 6:265 DCC and works only if the failure justifies it and the other party is in default where required. If you stop performing on an invalid termination, you may be in breach yourself; have a Dutch lawyer check the letter first.
What is a termination agreement under Dutch law?
A termination agreement (beëindigingsovereenkomst) is a contract by which the parties end their existing contract by mutual consent. Dutch law does not prescribe a general form for it. An oral agreement is valid, but hard to prove, so put it in writing.
A good termination agreement covers at least: the end date; what happens to orders, deliveries, stock and payments still outstanding; the return of documents, data and goods; which clauses survive the end (for example confidentiality, non-compete, liability, governing law and jurisdiction); and whether the parties grant each other a full and final release (finale kwijting).
If the parties end a dispute or uncertainty about their legal relationship, their agreement is usually a settlement agreement (vaststellingsovereenkomst). Such an agreement binds the parties even where it deviates from the legal position that existed before (Article 7:900(1) DCC).
A termination agreement is different from a unilateral termination. The other party does not have to accept a notice, a rescission or an annulment. Such a statement takes effect once it has reached the other party (Article 3:37(3) DCC), whether or not that party agrees with it. If it disagrees, the court decides whether the termination was valid.
Can you end a long-term contract by giving notice?
Dutch law has no general statutory rule on terminating long-term contracts (duurovereenkomsten), such as distribution, supply, licence or cooperation agreements. The Supreme Court has developed the following rules.
No notice clause. Whether, and on what conditions, a contract for an indefinite period can be terminated depends on its content and on the applicable statutory provisions. If neither the law nor the contract regulates termination, the contract can in principle be terminated by notice. Reasonableness and fairness (redelijkheid en billijkheid, Article 6:248(1) DCC) may, depending on the nature and content of the contract and the circumstances, require a sufficiently weighty reason for the termination, a certain notice period, or an offer to pay compensation (Supreme Court 28 October 2011, ECLI:NL:HR:2011:BQ9854, para. 3.5.1; Supreme Court 2 February 2018, ECLI:NL:HR:2018:141 (Goglio/SMQ), para. 3.6.2).
With a notice clause. If the law or the contract does regulate termination, the contract can in principle be terminated in accordance with that arrangement. Where the law and the contract leave room for it, reasonableness and fairness can still impose further requirements. Relying on a statutory or contractual right to terminate can also be unacceptable by standards of reasonableness and fairness (Article 6:248(2) DCC; Supreme Court 2 February 2018, ECLI:NL:HR:2018:141, paras. 3.6.3-3.6.4). In Goglio/SMQ, the Supreme Court upheld the appeal court’s finding that the agreed termination arrangement in a licence agreement was reasonable and needed no supplement, and dismissed the licensee’s appeal.
In 2025 the Supreme Court added that a court cannot simply set aside an agreed notice period and replace it with a longer one because the relationship has changed. The question is whether relying on the agreed period is unacceptable (Article 6:248(2) DCC). Reasonableness and fairness may, however, require the terminating party to offer compensation (Supreme Court 16 May 2025, ECLI:NL:HR:2025:763, paras. 3.2 and 3.4).
Fixed-term contracts. A contract for a fixed term can as a rule not be terminated early by notice, unless the contract or the law allows it. Important statutory exceptions are the client’s right to terminate a services agreement or a construction contract at any time (see below). Rescission for breach (Article 6:265 DCC) also remains available for fixed-term contracts, unless the contract validly excludes it. For leases of buildings (in case of a breach by the tenant), rescission can as a rule only be pronounced by the court (Article 7:231(1) DCC).
How does the termination notice process work?
A notice (opzegging) is a unilateral statement. Unless the law or the contract prescribes a form, it can be given in any form (Article 3:37(1) DCC). In practice, give notice in writing, so you can prove its content and date.
A notice should state which contract and which parties it concerns, that you terminate the contract, and the date on which it ends, taking into account the agreed or a reasonable notice period. Where you rely on a specific clause, refer to it. For a contract for an indefinite period without a notice clause, you do not in principle have to give reasons, but check whether reasonableness and fairness require a reason, a longer notice period or an offer of compensation (see above).
Some notices have a prescribed form. For a lease of business premises within the meaning of Article 7:290 DCC (such as retail and restaurant premises), notice of such a lease, which runs for five years or for more than five but less than ten years, must be given by bailiff’s writ or registered letter, with a notice period of at least one year (Article 7:293(2) DCC; see also Article 7:292 DCC).
What does a cancellation clause in a Dutch contract do?
Many contracts contain a cancellation or termination clause. Such a clause can extend or limit the statutory rights to end the contract. Parties are largely free to agree on this, subject to mandatory rules (for example for commercial agency and leases) and to reasonableness and fairness (Article 6:248 DCC).
Common cancellation clauses are:
- Termination for convenience: a right to give notice without a reason, with a fixed notice period.
- Termination for cause: a right to terminate with immediate effect for a serious breach, often after a cure period.
- Insolvency clause: a right to terminate if the other party is declared bankrupt or is granted a suspension of payments. Whether you can rely on it in an insolvency depends on the circumstances.
- Change of control clause: a right to terminate if the other party is taken over.
- Renewal and notice deadlines: the contract renews automatically unless notice is given before a set date.
If a clause does not regulate a situation, the statutory rules apply. For a breach, that means rescission under Article 6:265 DCC, including the requirement of default where performance is still possible.
If the clause is part of general terms and conditions, note that the Dutch rules on general terms (Articles 6:231-6:247 DCC) do not apply to contracts between businesses that are not both established in the Netherlands, whatever law governs the contract (Article 6:247(2) DCC). If Dutch law applies, a clause can then still be set aside where applying it would be unacceptable by standards of reasonableness and fairness (Article 6:248(2) DCC).
When can you rescind a contract for breach under Article 6:265 DCC?
The main statutory ground for ending a contract early is a failure in performance (tekortkoming). Every failure of a party to perform one of its obligations gives the other party the right to rescind the contract in whole or in part, unless the failure, given its special nature or minor importance, does not justify rescission with its consequences (Article 6:265(1) DCC).
The failure does not have to be attributable to the debtor; rescission is also possible where the debtor cannot perform because of force majeure. Where performance is not permanently or temporarily impossible, the right to rescind only arises once the debtor is in default (verzuim) (Article 6:265(2) DCC). As a rule, a creditor that is itself in default regarding the obligation concerned cannot rescind on that ground (Article 6:266(1) DCC).
Rescission takes place by a written statement of the party entitled to it. If the contract was concluded electronically, the statement can also be made electronically (Article 6:267(1) DCC). The court can also pronounce the rescission at that party’s request (Article 6:267(2) DCC). A partial rescission reduces the performances on both sides proportionally (Article 6:270 DCC).
Rescission is not the only remedy. The creditor can also claim performance (Article 3:296(1) DCC), claim damages (see below) or suspend its own performance until the other party performs (Article 6:262(1) DCC). In case of partial or improper performance, suspension is only allowed to the extent the failure justifies it (Article 6:262(2) DCC).
When is a party in default and what compensation follows?
Under Dutch law, a breach of contract is a failure to perform an obligation (tekortkoming). The debtor must compensate the damage the creditor suffers as a result, unless the failure cannot be attributed to the debtor (Article 6:74(1) DCC). Where performance is not already permanently impossible, damages are only due subject to the rules on default (Article 6:74(2) DCC).
Default (verzuim) arises when the debtor is given notice of default (ingebrekestelling) by a written warning setting a reasonable period for performance, and performance does not follow within that period (Article 6:82(1) DCC). If the debtor temporarily cannot perform, or its attitude shows that a warning would be useless, a written statement that it is held liable for the failure is sufficient (Article 6:82(2) DCC).
Default arises without notice (Article 6:83 DCC): (a) when a fixed deadline for performance expires without performance, unless the deadline has a different purpose; (b) when the obligation arises from a tort or is an obligation to pay damages under Article 6:74(1) DCC and is not performed immediately; and (c) when the creditor must infer from a statement of the debtor that the debtor will fail to perform.
The debtor is in default for as long as performance is not made after it has become due and the requirements of Articles 6:82 and 6:83 DCC are met, except to the extent that the delay cannot be attributed to the debtor or performance is already permanently impossible (Article 6:81 DCC).
If the contract is rescinded, the party whose failure was the ground for rescission must compensate the loss the other party suffers because the contract is rescinded instead of performed on both sides (Article 6:277(1) DCC). If the failure cannot be attributed to the debtor, this only applies within the limits of Article 6:78 DCC (Article 6:277(2) DCC).
Damages compensate financial loss, and other loss only to the extent the law grants a right to it (Article 6:95(1) DCC).
How do you make a formal request for termination?
Step 1: check the contract. Look for termination and notice clauses, cure periods, requirements of form and address, the governing law and any forum or arbitration clause.
Step 2: put the other party in default. If the other party fails to perform and performance is still possible, send a written notice of default with a reasonable period for performance (Article 6:82(1) DCC), unless default arises without notice (Article 6:83 DCC).
Step 3: send a rescission statement. If performance does not follow within that period, rescind the contract by written statement (Article 6:267(1) DCC). State which contract you rescind, whether in whole or in part, which failure you rely on, and that you reserve your right to damages (Article 6:277 DCC).
Step 4: if the other party disputes it. The court decides. The party relying on the legal consequences of facts or rights it asserts bears the burden of proving them, unless a special rule or reasonableness and fairness lead to a different allocation (Article 150 Dutch Code of Civil Procedure, DCCP). You can also ask the court to pronounce the rescission (Article 6:267(2) DCC).
If you are about to send a notice of default, a rescission statement or a termination agreement, our contract lawyers in the Netherlands can review the contract and the wording with you before it goes out.
How do you notify the other party of termination?
A statement addressed to a specific person only takes effect once it has reached that person (Article 3:37(3) DCC). A statement that did not reach the addressee, or not in time, still takes effect if this is the result of the addressee’s own act, the act of persons for whom it is liable, or other circumstances concerning its person that justify that it bears the disadvantage.
In a dispute, the sender must be able to prove that the statement arrived. Send a notice or rescission statement to the addresses stated in the contract, by registered post and by email, and keep the proof of sending and delivery. Where the law requires a written statement, it can also be served by a bailiff (Article 3:37(2) DCC).
Check whether the contract requires a particular method of notice, such as registered letter or a specific email address. Following that method avoids discussion about whether the notice was validly given.
Which notice periods must you observe?
Dutch law has no general statutory notice period for commercial contracts. First apply the notice period in the contract. If there is none and the contract is for an indefinite period, reasonableness and fairness may require a certain notice period (Supreme Court 28 October 2011, ECLI:NL:HR:2011:BQ9854, para. 3.5.1). In that judgment, the Supreme Court considered, among other things, whether the other party had made investments it still had to recoup and whether it needed time to adapt to the new situation (para. 3.6.2).
Some contracts have statutory notice periods. A commercial agency agreement for an indefinite period can be terminated with the agreed notice period; without agreement, the period is four months, plus one month after three years and two months after six years (Article 7:437(1) DCC). An agreed period may not be shorter than one month in the first year, two months in the second year and three months in the following years. If the parties agree on longer periods, the period for the principal may not be shorter than for the agent. Notice must be given for the end of a calendar month (Article 7:437(2)-(3) DCC).
A party that ends an agency agreement without respecting its term or the notice period and without the other party’s consent is liable for damages, unless it ends the agreement for an urgent reason communicated to the other party without delay (Article 7:439(1) DCC). Leases also have their own statutory notice rules.
Important: An agreed notice period is not always the end of the matter. Reasonableness and fairness can require a reason, a longer period or an offer of compensation, and relying on an agreed right to terminate can in exceptional cases be unacceptable (Article 6:248; Supreme Court 2018 and 2025). For a long-term distribution, supply or licence relationship, have a Dutch lawyer assess the position before giving notice.
When may you not end an agreement early?
You may not end a contract early if neither the contract nor the law gives you that right and there is no ground for rescission or annulment. An invalid termination does not have its intended effect. If you then stop performing, you may yourself be in breach of contract and liable for damages.
Even an agreed right to terminate may not be relied upon where that would be unacceptable by standards of reasonableness and fairness (Article 6:248(2) DCC; Supreme Court 2 February 2018, ECLI:NL:HR:2018:141, para. 3.6.4).
Leases have mandatory protection for the tenant. If a landlord terminates a residential lease and the tenant does not agree, the court can only grant the landlord’s claim on the grounds listed in Article 7:274(1) DCC. For business premises within Article 7:290 DCC let for more than two years (Article 7:301(1) DCC), a lease terminated by the landlord continues, unless the tenant agrees in writing, until the court has given a final (irrevocable) decision (unless the court declares its judgment provisionally enforceable) (Article 7:295(1) DCC), and the court can only end it on the grounds set out in Article 7:296 DCC.
Which special termination rules apply to services, construction and agency contracts?
Services agreement (overeenkomst van opdracht). The client can terminate a services agreement at any time (Article 7:408(1) DCC). A service provider acting in the course of a profession or business can, apart from serious reasons (gewichtige redenen), only terminate if the contract is for an indefinite period and does not end by completion (Article 7:408(2) DCC). A consumer client owes no damages for terminating, without prejudice to the reimbursement of costs under Article 7:406 DCC (Article 7:408(3) DCC). The contract can deviate from Article 7:408(1) DCC, but not to the detriment of a consumer client (Article 7:413(1)-(2) DCC).
If a services agreement ends before the work is completed or before its term expires, and the fee depends on completion or on the expiry of that term, the service provider is entitled to a reasonable part of the fee. The full fee is only due if the end of the contract is attributable to the client and payment of the full fee is reasonable in all the circumstances; savings resulting from the early end are deducted (Article 7:411 DCC).
Construction contract (aanneming van werk, Article 7:750 DCC). The client may terminate a construction contract in whole or in part at any time (Article 7:764(1) DCC). The client must then pay the price for the whole work, less the savings the contractor makes as a result of the termination, against delivery of the work completed so far. If the price depended on the costs actually incurred, the price is calculated on the basis of the costs incurred, the work done and the profit the contractor would have made on the whole work (Article 7:764(2) DCC).
Article 7:764 DCC gives this right only to the client. A contractor that wants to end the contract has to rely on the contract or on the general rules, such as rescission for breach (Article 6:265 DCC). Check the contract and any general conditions it incorporates, as they often contain their own termination rules.
Commercial agency (agentuurovereenkomst). Besides the notice periods of Article 7:437 DCC, each party can ask the subdistrict court to dissolve the agency agreement for an urgent reason or for a change in circumstances of such a nature that fairness requires the agreement to end immediately or shortly (Article 7:440(1) DCC). At the end of the agreement, the agent may be entitled to a goodwill indemnity (klantenvergoeding), see the next section. These agency rules do not cover distribution agreements; the Supreme Court rules on long-term contracts described above apply to them.
Can you annul a contract for mistake, fraud, threat or abuse of circumstances?
Annulment is not a remedy for breach; it deals with a defect at the time the contract was made, and only the party affected can invoke it. A contract made under a mistake (dwaling) that would not have been concluded with a correct view of the facts is voidable: (a) if the mistake is due to information given by the other party, unless that party could assume that the contract would have been concluded without that information; (b) if the other party, given what it knew or should have known about the mistake, should have informed the mistaken party; or (c) if the other party made the same incorrect assumption, unless it did not need to understand, even with a correct view of the facts, that the mistaken party would then not have concluded the contract (Article 6:228(1) DCC). Annulment cannot be based on a mistake that relates only to a future circumstance, or that should remain at the risk of the mistaken party given the nature of the contract, generally accepted views or the circumstances (Article 6:228(2) DCC).
A contract is also voidable if it was brought about by threat, fraud or abuse of circumstances (Article 3:44(1) DCC). Fraud requires an intentionally incorrect statement, the intentional concealment of a fact that had to be disclosed, or another trick; general sales talk, even if untrue, is not in itself fraud (Article 3:44(3) DCC). Abuse of circumstances exists where someone who knows or should understand that another person is induced to conclude the contract by special circumstances, such as necessity, dependence, rashness, an abnormal mental state or inexperience, promotes the contract although what he knows or should understand ought to have held him back (Article 3:44(4) DCC).
Annulment takes place by an out-of-court statement or by a court judgment (Article 3:49 DCC) and works retroactively to the moment the contract was made (Article 3:53(1) DCC). In the case of abuse of circumstances, the right to annul lapses if the other party proposes in time an amendment of the contract that adequately removes the disadvantage (Article 3:54(1) DCC).
When can you invoke force majeure or unforeseen circumstances?
Dutch law calls force majeure overmacht. A failure cannot be attributed to the debtor if it is not due to its fault and is not for its account under the law, a juridical act (such as the contract) or generally accepted views (Article 6:75 DCC).
Article 6:75 DCC does not contain a list of events. Whether a pandemic, a strike, a supply problem or a price increase is force majeure depends on the contract and the circumstances. That is why many contracts contain a force majeure clause that defines the events and their consequences, such as suspension, notification duties and a right to terminate after a certain period.
Force majeure protects the debtor against a claim for damages (Article 6:74(1) DCC). It does not prevent rescission: Article 6:265 DCC applies to every failure in performance, attributable or not. In that case the damages under Article 6:277(1) DCC are only due within the limits of Article 6:78 DCC (Article 6:277(2) DCC). The other party can also suspend its own performance (Article 6:262 DCC).
Unforeseen circumstances (onvoorziene omstandigheden) are a separate ground. At the request of a party, the court can amend the effects of a contract or rescind it in whole or in part because of unforeseen circumstances of such a nature that the other party, by standards of reasonableness and fairness, may not expect the contract to be maintained unaltered. The court can give the amendment or rescission retroactive effect (Article 6:258(1) DCC).
The court will not do so to the extent the circumstances are for the account of the party invoking them, by the nature of the contract or generally accepted views (Article 6:258(2) DCC). Article 6:258 DCC does not give a party a unilateral right to terminate or an obligation to renegotiate; it requires a court decision.
How this works out depends on the type of contract:
- One-off contracts, such as a single sale: if performance becomes permanently or temporarily impossible, the creditor can rescind without first putting the debtor in default (Article 6:265(2) DCC), unless the failure is too minor to justify rescission.
- Long-term contracts: a temporary impediment often leads to suspension and consultation under the force majeure clause. If the contract does not regulate this, notice, rescission or a claim under Article 6:258 DCC may be considered.
What happens after a contract has ended?
After rescission, the parties are released from the obligations affected. Performances already made keep their legal basis, but each party must undo what it has received (Article 6:271 DCC). If the nature of the performance excludes undoing, for example services already provided, a payment equal to its value at the time of receipt takes its place (Article 6:272(1) DCC).
Some clauses are meant to survive the end of the contract, such as confidentiality, non-compete, liability and dispute resolution clauses. Check the contract, and record in a termination agreement which clauses continue to apply.
A commercial agent may be entitled to a goodwill indemnity (klantenvergoeding) if it brought in new customers or considerably increased business with existing customers that still gives the principal substantial benefits, and the payment is fair. The indemnity is at most one year’s remuneration, calculated on the average of the last five years (or of the whole term if shorter). The agent loses the right if it does not claim the indemnity within one year after the end of the agreement, and the indemnity is not due in the cases of Article 7:442(4) DCC (Article 7:442(1)-(3) DCC).
How long can you still terminate or void a contract?
A legal claim to rescind a contract for a failure in performance becomes time-barred five years after the start of the day following the day on which the creditor became aware of the failure, and in any event twenty years after the failure arose (Article 3:311(1) DCC). Once that claim is time-barred, the right to rescind out of court also lapses, but rescission can still be invoked to fend off a claim based on the contract (Article 6:268 DCC).
A claim to annul a contract becomes time-barred three years after, for example, the mistake or fraud was discovered, or the threat or abuse of circumstances ceased to have effect (Article 3:52(1) DCC). After that, annulment by out-of-court statement on the same ground is no longer possible (Article 3:52(2) DCC), but a ground for annulment can still be invoked at any time to fend off a claim based on the contract (Article 3:51(3) DCC). A claim for damages becomes time-barred five years after the start of the day following the day on which the injured party became aware of both the damage and the liable person, and in any event twenty years after the event that caused the damage (Article 3:310(1) DCC); the following paragraphs of that article contain exceptions.
When should you involve a Dutch lawyer?
Involve a Dutch lawyer before you send a notice, a notice of default or a rescission statement, when the other party disputes that your termination is valid, and before you stop performing on the strength of a termination. Remko Roosjen and our contract lawyers in the Netherlands can review the contract, the route and the timeline with you.
Frequently asked questions about terminating an agreement under Dutch law
What is the difference between terminating, rescinding and annulling a contract?
Termination by notice (opzegging) ends a long-term contract for the future and needs no breach. Rescission (ontbinding) responds to a failure in performance (Article 6:265 DCC) and in principle has no retroactive effect (Article 6:269 DCC). Annulment (vernietiging) deals with a defect when the contract was made, such as mistake or fraud, and works retroactively (Article 3:53(1) DCC).
Can you terminate a contract because of force majeure under Dutch law?
Force majeure (overmacht, Article 6:75 DCC) means the failure cannot be attributed to the debtor, so no damages are owed under Article 6:74 DCC. The other party can still rescind, because Article 6:265 DCC applies to every failure, unless it is too minor to justify rescission. A force majeure clause in the contract may regulate this differently.
How do I know if my contract is voidable?
A contract is voidable if it was made under a mistake as described in Article 6:228 DCC, or under threat, fraud or abuse of circumstances (Article 3:44 DCC). You annul it by an out-of-court statement or through the court (Article 3:49 DCC); the claim becomes time-barred three years after, for example, the mistake or fraud was discovered (Article 3:52(1) DCC).
Can a client terminate a construction contract early under Article 7:764 DCC?
Yes. The client may terminate a construction contract in whole or in part at any time (Article 7:764(1) DCC). It then pays the price for the whole work, less the contractor’s savings, against delivery of the work completed so far (Article 7:764(2) DCC). A client can also terminate a services agreement at any time (Article 7:408(1) DCC).
What does breach of contract mean under Dutch law?
A breach of contract is a failure to perform an obligation (tekortkoming). Fault is not required: the debtor owes damages unless the failure cannot be attributed to it (Articles 6:74(1) and 6:75 DCC), and where performance is still possible only after default (Article 6:74(2) DCC). The creditor can also rescind the contract (Article 6:265 DCC).
Primary sources
The statutory texts are in Dutch and link to the current version on wetten.overheid.nl; the judgments link to rechtspraak.nl.
- Dutch Civil Code Book 3: Articles 3:37, 3:44, 3:49, 3:51, 3:52, 3:53, 3:54, 3:296, 3:310 and 3:311
- Dutch Civil Code Book 6: Articles 6:74, 6:75, 6:78, 6:81, 6:82, 6:83, 6:95, 6:228, 6:247, 6:248, 6:258, 6:262, 6:265, 6:266, 6:267, 6:268, 6:269, 6:270, 6:271, 6:272 and 6:277
- Dutch Civil Code Book 7: Articles 7:271, 7:274, 7:290, 7:292, 7:293, 7:295, 7:296, 7:406, 7:408, 7:411, 7:413, 7:437, 7:439, 7:440, 7:442, 7:750, 7:764 and 7:900
- Dutch Code of Civil Procedure: Article 150
- Supreme Court 28 October 2011, ECLI:NL:HR:2011:BQ9854
- Supreme Court 2 February 2018, ECLI:NL:HR:2018:141 (Goglio/SMQ)
- Supreme Court 16 May 2025, ECLI:NL:HR:2025:763