A legal dispute is a disagreement about rights or obligations that the parties cannot settle themselves. It is settled by negotiation, mediation, arbitration or in court. Claims up to €25,000 generally go to the subdistrict court (Article 93 Dutch Code of Civil Procedure, DCCP); larger ones to the district court, where a lawyer is usually required (Article 79 DCCP).

In short

  • Cases usually start with a writ of summons served by a bailiff; a petition is used where the law so provides.
  • A final judgment binds the same parties in later proceedings; appeal is as a rule possible within three months, but not for claims up to €1,750.
  • Alternatives to court are negotiation, mediation, binding advice and arbitration; the contract may already determine which route applies.
  • Limitation periods and arbitration or forum clauses can decide whether and where a claim can be brought; have a Dutch lawyer check them before you act.

Before taking action, check three things: which law applies to the dispute, which court or arbitral tribunal has jurisdiction, and whether the claim is time-barred. To discuss a specific dispute, contact Remko Roosjen at MAAK Advocaten. For disputes with a contractor, see our page on a dispute with a Dutch contractor.

Whether you need a lawyer depends on the court; the rules are explained in the sections on the court system and on lawyers below. For the settlement side of a dispute, see commercial dispute settlement in the Netherlands.

Below we explain how Dutch civil litigation works, which types of dispute arise, which rules apply to a claim, what a court ruling means and which alternatives to court exist.

How does the Dutch civil litigation system work?

Dutch civil litigation is governed by the Dutch Code of Civil Procedure (Wetboek van Burgerlijke Rechtsvordering). Commercial claims usually start with a writ of summons (dagvaarding) served by a bailiff (Articles 78 and 111 DCCP); some matters start with a petition (verzoekschrift) because the law so provides (Article 261 DCCP).

Which court hears a case depends on the type of case and the amount claimed. The subdistrict court deals with claims of up to €25,000 and, regardless of the amount, with employment, agency, rent and consumer sale cases, among others (Article 93 DCCP). Court fees (in Dutch “griffierechten“) are charged in cases started by writ of summons from each claimant and each defendant who appears, for each instance (Article 3(1) Court Fees in Civil Cases Act). The amount depends on the value of the claim and the type of party and follows from the table annexed to that Act, which can be indexed every year (Article 3(5) and Article 2). This court fee list gives the current amounts.

At first instance, the case goes to one of the district courts (rechtbanken), to the civil section or to the subdistrict court. A clause designating a Dutch court makes that court exclusively competent unless the contract provides otherwise (Article 108(1) DCCP), but within that court the cases listed in Article 93 DCCP are still heard by the subdistrict court. The Supreme Court (Hoge Raad) in The Hague is the highest court; in civil cases it hears appeals in cassation.

After the writ of summons and the statement of defence, the court usually holds an oral hearing, at which it can also try to bring about a settlement (Articles 87 and 131 DCCP). It then gives judgment. The losing party is in principle ordered to pay the costs of the proceedings (Article 237 DCCP). The full procedure is explained in our article on proceedings on the merits in the Netherlands.

What is Dutch civil law?

Dutch civil law is codified, mainly in the Dutch Civil Code (Burgerlijk Wetboek, DCC). Contract law and tort are in Book 6, and specific contracts such as sale, lease and services are in Book 7.

A court decides the case before it; it may not decide cases by way of a general regulation, disposition or rule (Article 12 General Provisions Act).

Civil law governs disputes between private parties, such as contract and property claims.

In a civil case, the claimant states its claim and the grounds for it in the writ of summons (Article 111 DCCP), and the defendant responds in a statement of defence (Article 128 DCCP). The party that invokes the legal consequences of facts it alleges must prove those facts, unless a special rule or reasonableness and fairness requires otherwise (Article 150 DCCP).

A claim requires sufficient interest: without it, no one has a right of action (Article 3:303 DCC). Claims are also subject to limitation. A claim for performance of a contractual obligation to give or to do is time-barred five years after the beginning of the day following the day on which it became due (Article 3:307(1) DCC). A claim for damages is time-barred five years after the beginning of the day following the day on which the injured party became aware of both the damage and the liable person, and in any event twenty years after the event that caused the damage (Article 3:310(1) DCC); different periods apply in some cases, for example for performance after an indefinite period, for pollution damage and for personal injury (Article 3:307(2) and Article 3:310(2) and (5) DCC).

How does the judicial process work?

Dutch civil courts operate at three levels, with a separate English-language chamber for international commercial cases.

The levels are:

  • District courts (“rechtbanken“) – hear civil cases at first instance. The subdistrict court (kantonrechter) is part of the district court and hears the cases listed in Article 93 DCCP. Cases are decided by a single judge or, as a rule, a chamber of three judges (Article 6 Judiciary Organisation Act).
  • Courts of appeal (“gerechtshoven“) – hear appeals against judgments of the district courts in their region (Article 60(1) Judiciary Organisation Act). The appeal period is as a rule three months (Article 339(1) DCCP) and four weeks in summary proceedings (Article 339(2) DCCP). No appeal lies if the claim did not exceed €1,750, unless the law provides otherwise (Article 332(1) DCCP).
  • Supreme Court (“Hoge Raad“) – hears appeals in cassation, which must as a rule be lodged within three months (Articles 398 and 402 DCCP). It reviews whether the law (other than the law of foreign states) was correctly applied and whether formal requirements were observed (Article 79(1) Judiciary Organisation Act), and it is bound by the facts as established by the lower court (Article 419(3) DCCP).
  • Netherlands Commercial Court (“NCC“) – the international commercial chamber of the Amsterdam District Court, with the Netherlands Commercial Court of Appeal at the Amsterdam Court of Appeal. Parties can litigate there in English if the Amsterdam court has jurisdiction, the dispute is international and concerns a legal relationship at the parties’ free disposal, and the parties have expressly agreed to it (the agreement is proved by a written document). Subdistrict court cases are excluded. The preliminary relief judge of those courts can also hear urgent cases in English (Article 32a(1) and (3) DCCP).

Administrative and tax disputes follow separate rules of administrative law. Arbitration is not a state court but a private alternative based on an agreement between the parties (Article 1020 DCCP).

Businesses in the Netherlands face, among others, the following types of legal dispute.

Each type has its own legal framework and, sometimes, its own court.

Contract disputes are common in commercial practice: non-payment, late or defective performance, or a dispute about what was agreed. The other party can claim performance (Article 3:296 DCC), damages for a failure in performance that can be attributed to the debtor (Article 6:74 DCC), or terminate the contract, unless the failure, given its special nature or minor importance, does not justify termination (Article 6:265(1) DCC). Termination takes place by written notice or, at the request of a party, by the court (Article 6:267 DCC). Employment and rent disputes go to the subdistrict court (Article 93(c) DCCP).

Intellectual property disputes concern, for example, trademark or copyright infringement. Because an infringement can cause ongoing damage, these disputes can start with summary proceedings (kort geding) for an injunction, which are available in urgent matters in which an immediate provisional measure is required (Article 254(1) DCCP).

Corporate and shareholder disputes concern, for example, deadlock between shareholders or the conduct of directors. Some follow special procedures, such as an inquiry into the policy and conduct of affairs of a legal entity, ordered by the Enterprise Chamber of the Amsterdam Court of Appeal on the request of those entitled to apply for it (Article 2:345(1) DCC; the applicants are listed in Articles 2:346 and 2:347 DCC).

Real estate disputes concern, for example, the purchase, construction or lease of property. Rent disputes, including those about business premises, are heard by the subdistrict court regardless of the amount (Article 93(c) DCCP).

Commercial disputes often arise from a few recurring causes.

One frequent cause is the contract itself. Contracts often contain ambiguities or gaps that only surface during performance. Under Dutch law, a written contract is not interpreted on its wording alone: what matters is the meaning the parties could reasonably attribute to its terms in the circumstances and what they could reasonably expect from each other (HR 13 March 1981, ECLI:NL:HR:1981:AG4158, Haviltex, r.o. 2).

Another source of conflict is disagreement between shareholders, or between a company and its directors, about their rights and duties. In these cases, the parties often disagree on who has which rights and responsibilities under the law and the articles of association.

Clear contract terms help to prevent disputes and make them easier to settle, in particular a choice of law and a forum or arbitration clause.

Civil procedure provides a route to a binding and enforceable decision when negotiation fails.

Before or during proceedings, the parties can still settle. A settlement agreement (vaststellingsovereenkomst) binds the parties, also where it deviates from the previous legal position (Article 7:900(1) DCC).

Mediation and arbitration differ fundamentally. In mediation, a neutral mediator helps the parties reach their own agreement; the mediator does not decide. In arbitration, one or more arbitrators give a binding award. Arbitration requires an arbitration agreement (Article 1020 DCCP), and once an award is final (in kracht van gewijsde), its decisions on the legal relationship in dispute have the force of res judicata in other proceedings between the same parties, with effect from the day the award was made (Article 1059(1) DCCP).

In court proceedings, the parties exchange written statements, the court usually holds an oral hearing and may order the taking of evidence, and then gives judgment. Once a judgment can no longer be challenged by ordinary legal remedies, its decisions on the legal relationship in dispute bind the same parties in later proceedings (Article 236(1) DCCP). On request, the court can declare the judgment provisionally enforceable, even if an appeal is lodged (Article 233 DCCP).

Interim measures are also available: summary proceedings in urgent matters (Article 254 DCCP) and, with leave of the preliminary relief judge, a prejudgment attachment (conservatoir beslag) to secure a claim (Article 700(1) DCCP).

A claim must meet a few basic requirements under Dutch law.

First, the claimant must have sufficient interest in the claim (Article 3:303 DCC).

Second, the claim must not be time-barred. Unless the law provides otherwise, a claim is time-barred after twenty years (Article 3:306 DCC), but many claims have shorter periods, such as the five-year periods for contractual performance and for damages (Articles 3:307 and 3:310 DCC). For a claim for performance of an obligation, limitation is interrupted by a written demand or a written notice in which the creditor unequivocally reserves its right to performance; for other claims, such as a claim for termination or annulment, a written demand interrupts limitation if it is followed within six months by another act of interruption, such as issuing proceedings (Article 3:317 DCC).

Third, the writ of summons must state the claim and its grounds, the defences the defendant has already raised and the grounds for them, and the evidence and witnesses the claimant can offer for the disputed grounds (Article 111(2)(d) and (3) DCCP).

Important: Limitation can end a claim before a court looks at the merits (Articles 3:306, 3:307 and 3:310 DCC). Whether a letter interrupted the period depends on its content and on the type of claim, so the letters you sent and their dates matter. Have a Dutch litigation lawyer review the limitation position before you rely on a demand letter or wait with proceedings.

What are the consequences of a court ruling in the Netherlands?

A court bases its judgment on the applicable Dutch legislation, EU law where relevant and general principles of law.

Once a judgment is final, its decisions on the legal relationship in dispute bind the same parties and their successors in other proceedings (Article 236(1) and (2) DCCP); it does not bind third parties in the same way.

A party that disagrees with a first-instance judgment can as a rule appeal within three months, or within four weeks in summary proceedings (Article 339 DCCP), unless the claim did not exceed €1,750 (Article 332(1) DCCP). An appeal suspends the enforcement of the judgment, unless the judgment was declared provisionally enforceable (Article 350(1) DCCP; Article 233 DCCP).

The losing party is in principle ordered to pay the costs of the proceedings (Article 237(1) DCCP), and the court fixes in the judgment the costs incurred before the judgment (Article 237(3) DCCP). An order to do or not to do something can be reinforced with a penalty payment (dwangsom), but not an order to pay money; the penalty cannot be forfeited before the judgment has been served (Article 611a(1) and (3) DCCP).

What practical points should foreign parties consider?

For a foreign business, the practical points in Dutch litigation are language, representation, costs and enforcement.

Proceedings before the Dutch courts are generally conducted in Dutch; English is possible before the Netherlands Commercial Court if the parties have agreed to it (Article 32a DCCP). Outside the subdistrict court, a party as a rule must be represented by a Dutch lawyer (Article 79 DCCP), except a defendant in summary proceedings, who may also appear in person (Article 255(1) DCCP), and each party pays a court fee. Finally, the value of a judgment depends on the debtor’s assets. If the debtor is declared bankrupt, pending proceedings for payment from the estate are suspended, and they only continue if the claim is disputed in the verification procedure (Article 29 Bankruptcy Act).

To reduce the risk that a judgment cannot be enforced, a creditor can ask for leave to levy a prejudgment attachment on the debtor’s assets before or during the proceedings (Article 700 DCCP).

What should you check before a dispute escalates?

Three points shape how a dispute develops: the contract, the available evidence and whether the other party is in default.

The contract determines which law applies, which court or arbitral tribunal is designated, and whether notice requirements or time limits apply.

Evidence can be secured under the Code of Civil Procedure. A party to a legal relationship can, under conditions, claim access to, a copy of or an extract from specific data about that relationship if it has sufficient interest, unless the holder has a right of non-disclosure or there are compelling reasons against it (Article 194 DCCP). Before the case is entered on the docket, a party can ask the court for one or more provisional evidence measures, such as a witness hearing or expert report (Article 196 DCCP).

Where performance is not permanently impossible, damages for delay and termination of a contract require that the debtor is in default (verzuim) (Articles 6:74(2) and 6:265(2) DCC). Default usually arises after a written notice of default setting a reasonable period for performance, if performance does not follow within that period (Article 6:82(1) DCC); a written notice holding the debtor liable can suffice if the debtor is temporarily unable to perform or a demand would be pointless (Article 6:82(2) DCC). Default can also arise without notice, for example when a fixed deadline for performance passes (Article 6:83 DCC).

Which alternatives to court proceedings exist?

The main types of alternative dispute resolution (ADR) in the Netherlands are mediation, arbitration, negotiation and binding advice.

They differ in who decides and how binding the outcome is:

  • Mediation – a neutral mediator helps the parties negotiate. Participation is voluntary and the mediator does not decide; the result only binds the parties if they record it in a settlement agreement (Article 7:900 DCC).
  • Arbitration – one or more arbitrators decide the dispute in a binding award. It requires an arbitration agreement, concluded before or after the dispute arises (Article 1020(1) and (2) DCCP), and it cannot lead to legal consequences that are not at the parties’ free disposal (Article 1020(3)). A court must decline jurisdiction if a party invokes the arbitration agreement before any other defence, unless the agreement is invalid (Article 1022 DCCP). An award made in the Netherlands can be enforced there once the preliminary relief judge of the court at the place of arbitration has granted leave (Article 1062(1) DCCP).
  • Negotiation and binding advice – the parties negotiate directly, or ask a third party to determine their legal relationship in a binding advice (bindend advies); a settlement agreement can also arise from a decision entrusted to a third party (Article 7:900(2) DCC).

Arbitration can be administered by an institution under its own rules or organised by the parties themselves (ad hoc). The arbitration clause in the contract determines which applies.

Important: A clause designating a Dutch court generally has no effect for claims of up to €25,000 or for an individual employment contract (and certain other cases), unless it was agreed after the dispute arose or the employee, the non-business party or the tenant applies to the designated court (Article 108(2) DCCP). Have a Dutch litigation lawyer read the clause before you start proceedings or respond to a writ.

Which role do lawyers and mediators play?

Lawyers advise on the legal position, negotiate on behalf of their clients and represent them in court and in arbitration. Before the subdistrict court (kantonrechter), parties can litigate in person or through an authorised representative (Articles 79(1) and 80(1) DCCP). In other cases started by writ of summons, a party cannot litigate in person but only through a lawyer (advocaat) (Article 79(2) DCCP), although in summary proceedings the defendant may also appear in person (Article 255(1) DCCP); on appeal, a lawyer is as a rule required (Article 353(1) DCCP).

A mediator is a neutral third party who helps the parties find their own solution. The mediator does not give a decision.

Which route is most efficient depends on the case. Mediation works if both parties are willing to negotiate; court proceedings or arbitration lead to a binding decision even if one party is unwilling.

For an overview of the courts, costs and procedures, see our page on litigation in the Netherlands.

Frequently asked questions about legal disputes in the Netherlands

What does legal dispute mean?

A legal dispute is a disagreement between two or more parties about their rights or obligations, for example under a contract, that they cannot settle themselves. Under Dutch law, a party needs sufficient interest to bring a claim (Article 3:303 DCC).

What are the types of alternative dispute resolution in the Netherlands?

They are negotiation, mediation, binding advice and arbitration. In mediation, a neutral mediator helps the parties agree without deciding. In a binding advice (bindend advies) the parties ask a third party to decide; this can establish a settlement agreement (Article 7:900(2) DCC). Arbitration leads to a binding award and requires an arbitration agreement (Article 1020 DCCP).

Which disputes are handled in court?

A civil dispute can be brought before the Dutch courts if no arbitration agreement applies and a Dutch court has jurisdiction. The subdistrict court hears claims of up to €25,000 and, regardless of the amount, employment, agency, rent and consumer sale cases; other cases go to the civil section of the district court (Article 93 DCCP).

What legal remedies can a Dutch court grant?

A court can order performance (Article 3:296 DCC), award damages (Articles 6:74 and 6:162 DCC), terminate a contract at a party’s request (Article 6:267(2) DCC) or declare the parties’ rights (Article 3:302 DCC). Damages cover financial loss and, where the law provides for it, other harm (Article 6:95 DCC). A penalty payment can reinforce an order (Article 611a DCCP).

How does arbitration work in the Netherlands?

Arbitration requires an arbitration agreement (Article 1020(1) and (2) DCCP). If a party invokes it before any other defence, the Dutch court must decline jurisdiction unless the agreement is invalid (Article 1022 DCCP), but interim measures and summary proceedings remain available (Article 1022a DCCP). An award made in the Netherlands is enforced with leave (Article 1062 DCCP).

Primary sources