Published on · Last updated
If your Dutch contractor does not perform, performs late or delivers defective work, you as the client (opdrachtgever) can claim repair, damages or dissolution. This is a construction contract (aanneming van werk, Article 7:750 Dutch Civil Code, DCC). After delivery, you must in principle first give the contractor a reasonable period to remedy defects (Article 7:759 DCC).
In short
- Against a Dutch contractor, damages or dissolution usually require default, which in most cases means a written notice with a reasonable period to perform (Article 6:82 Dutch Civil Code).
- Accepting the work generally releases the contractor from liability for defects you should have discovered, but not for building works under newer contracts (Article 7:758(3)-(4)).
- A lawyer should step in when the contractor disputes defects, stops working or bills unagreed extra work, since your notice and its deadline decide whether damages or dissolution stay open.
Under Article 7:750(1) DCC, a construction contract is an agreement under which one party, the contractor, undertakes towards the client, outside employment, to create and deliver a work of a material nature for a price in money to be paid by the client. The contractor may have the work carried out by others, such as subcontractors, under his direction, but remains liable for proper performance (Article 7:751 DCC). For building works (bouwwerken), the Quality Assurance for Building Act (Wet kwaliteitsborging voor het bouwen) added stricter rules, several of which only apply to contracts concluded on or after 1 January 2024, when the Act entered into force (Stb. 2023, 113; for Article 7:757a with retroactive effect, Stb. 2024, 19; Article 218 Transitional Act new Civil Code).
What rights do you have when your Dutch contractor breaches the contract?
If your contractor breaches the contract, you can in principle claim performance or repair (Article 3:296 DCC, Article 7:759 DCC), damages (Article 6:74 DCC) or dissolution of the contract (Article 6:265 DCC). You may also suspend your own payment to the extent the failure justifies it (Article 6:262 DCC). Damages and dissolution usually require that the contractor is first in default.
Breach of a construction contract takes many forms. The contractor does not carry out the work, delivers poor work, misses deadlines or damages your property. Every failure entitles you to dissolve the contract (where required, once the contractor is in default), unless the failure, given its special nature or minor importance, does not justify dissolution with its consequences (Article 6:265(1) DCC). In short, in principle only a failure of sufficient weight justifies dissolution (HR 28 September 2018, ECLI:NL:HR:2018:1810, para 3.5), and all circumstances of the case can matter in that assessment (para 3.8.1). A hairline crack may not justify dissolution, while a serious structural defect may.
Inspection plays a central role. Once the contractor states that the work is ready for delivery, you must inspect it within a reasonable period and either accept it, with or without reservation, or refuse it while indicating the defects. If you do neither, you are deemed to have accepted the work tacitly (Article 7:758(1) DCC). Report defects you discover later promptly and in writing: a creditor can no longer rely on a defect if he does not protest to the debtor within a reasonable time after discovering it or after he reasonably should have discovered it (Article 6:89 DCC). The law sets no fixed number of days.
Defects that were not visible at delivery are treated differently depending on the type of work. As a rule, the contractor is released from liability for defects that you should reasonably have discovered at the time of delivery (Article 7:758(3) DCC). For building works under contracts concluded on or after 1 January 2024, the contractor remains liable for defects not discovered at delivery, unless they cannot be attributed to him (Article 7:758(4) DCC). This cannot be waived to the detriment of a client who is a natural person not acting in a business or profession; for other clients only if the contract expressly says so. A claim for a defect becomes time-barred two years after you protested about it (or, if you gave the contractor a period to repair, from the end of that period, or earlier if the contractor has said that he will not repair the defect), and in any event twenty years after delivery for building works and ten years in other cases (Article 7:761 DCC).
A contractor who knew of a hidden defect and concealed it cannot exclude or limit his liability for it, nor subject it to shorter limitation periods than those of Article 7:761 DCC. Concealment by the persons he put in charge of the work counts as concealment by the contractor (Article 7:762 DCC).
How do you hold a Dutch contractor liable?
Holding a contractor liable usually starts with a written notice of default (ingebrekestelling) that describes the defect, demands repair within a reasonable period and states what you will do otherwise. In most cases the contractor is only in default once that period has passed without performance (Article 6:82 DCC); in some cases default arises without a notice (Article 6:83 DCC).
A notice of default needs a written demand that sets a reasonable period to perform (Article 6:82(1) DCC). What the letter should say and how it is sent depend on the contract and the facts, so have it reviewed before you send it.
Important: A notice of default starts the clock for what follows. It must give a reasonable period to perform, although default can also arise without one, for instance when a fixed deadline expires (Articles 6:82 and 6:83 DCC). Whether your letter qualifies can decide a later claim for damages or dissolution, so have a lawyer review it before it is sent.
Without a valid notice, the contractor is usually not yet in default, so you cannot yet claim damages for delay or dissolve the contract. There are exceptions. Default arises without notice when a fixed deadline expires (unless the deadline has a different purpose) or when the contractor tells you that he will not perform (Article 6:83(a) and (c) DCC). If the contractor is temporarily unable to perform, or his attitude shows that a reminder would be pointless, a written statement holding him liable is enough (Article 6:82(2) DCC).
Does the contractor fail to perform within the period? Then you can dissolve the construction contract in whole or in part by a written declaration (Article 6:267 DCC), referring to your notice. Dissolution has no retroactive effect, but it releases both parties from the obligations it affects (Articles 6:269 and 6:271 DCC): you no longer owe the price for work that is not carried out, and you can have the work completed by another contractor. Do not confuse this with cancellation (opzegging): you may cancel a construction contract at any time, but you then owe the full price minus the contractor’s savings (Article 7:764 DCC).
Performances already made must in principle be undone (Article 6:271 DCC). Work that by its nature cannot be undone is compensated at its value at the time you received it; if it did not conform to the contract, at the value it actually had for you (Article 6:272 DCC). Partial dissolution reduces both performances proportionally (Article 6:270 DCC). There is no fixed percentage formula; the outcome depends on the value of the work.
Do you want to know where you stand in a contractor dispute? Our litigation attorneys can review your contract documents and the notice of default before you send it.
What must you know about additional work and cost overruns under Dutch law?
Additional work (meerwerk) is an addition or change to the agreed work that you, the client, ask for. The contractor can only charge a higher price if he pointed out to you in good time that it would increase the price, unless you should have understood that yourself (Article 7:755 DCC).
Additional work is regulated in Article 7:755 DCC, not in Article 7:753. Article 7:753 DCC concerns cost-increasing circumstances that arise or come to light after the contract was concluded and cannot be attributed to the contractor: at his request, the court can then adjust the price, provided he did not have to take such circumstances into account when setting the price. Under both provisions the contractor must warn you in time (Article 7:753(3) DCC: as soon as possible). The law does not require the warning under Article 7:755 to be in writing, but written confirmation makes it easier to prove. Without a timely warning, the contractor as a rule cannot charge the extra price (Article 7:755 DCC).
The exception applies where you should have understood the need for a higher price yourself; that depends on the facts, for example how clearly the extra item changes the agreed work. Article 7:755 DCC cannot be deviated from to the client’s detriment, except by a standard regulation within the meaning of Article 6:214 DCC.
Reduced work (minderwerk) arises when part of the agreed work is not carried out. If you cancel part of the work, Article 7:764 DCC applies: you may cancel the contract at any time, in whole or in part, but you must pay the price for the whole work minus the savings that result for the contractor. Standard terms used in the construction sector may contain their own rules for settling additional and reduced work, so check your contract.
If no price was agreed, or only an indicative price (richtprijs), you owe a reasonable price; the court takes into account the prices the contractor usually charged and the expectations he raised (Article 7:752(1) DCC). An indicative price may not be exceeded by more than 10%, unless the contractor warned you as early as possible about the likelihood of a further overrun, so that you could still limit or simplify the work (Article 7:752(2) DCC). Provisional sums (stelposten) are amounts for parts whose cost is not yet known; how they are settled depends on the contract, so ask the contractor to document the actual costs.
The contractor also has a duty to warn. He must warn you about errors in the assignment that he knew or should reasonably have known, and about defects and unsuitability of materials or ground provided by you and errors in plans, drawings, calculations, specifications or instructions you provided (Article 7:754(1) DCC). For building works, the warning must be given in writing and unambiguously, pointing out in good time the possible consequences for proper performance; a consumer client cannot waive this (Article 7:754(2) DCC).
How do you handle damage during renovation in the Netherlands?
The contractor must compensate damage to your property caused during the work if it results from a failure to perform, unless that failure cannot be attributed to him (Article 6:74 DCC); it can also be a tort (Article 6:162 DCC). If your own conduct contributed, the damages may be reduced in proportion to your contribution, or divided differently if fairness requires (Article 6:101(1) DCC). Document the damage straight away with photographs and a written report.
Damage caused while carrying out the work is usually a failure to perform the contract (Article 6:74 DCC), and may also be a tort (Article 6:162 DCC). The contractor must work with due care. If his staff damage your floor with heavy equipment, he must pay for the repair. He is liable for the persons he uses, such as staff and subcontractors, as for his own conduct (Article 6:76 DCC; Article 7:751 DCC).
If the poor execution is due to defects or unsuitability of materials or tools used by the contractor, the consequences are for his account (Article 7:760(1) DCC). If it is due to defects in materials or ground supplied by you, or to errors in plans or drawings you provided, the consequences are for your account, unless the contractor breached his duty to warn or otherwise fell short in expertise or care (Article 7:760(2)-(3) DCC).
Report damage to the contractor straight away and confirm it in writing by email or letter. Photograph the damage from several angles, preferably with a date stamp, and note who witnessed it. These records matter if the contractor denies liability.
Does the contractor refuse to repair? After delivery, you must in principle first give the contractor the opportunity to remedy the defects within a reasonable period, unless this cannot be required of you in the circumstances (Article 7:759(1) DCC). You can demand repair, unless the costs are out of proportion to your interest in repair rather than damages (Article 7:759(2) DCC). As a rule, wait until the period has expired before you engage another party.
Some construction contracts limit the contractor’s liability. Such clauses do not always hold. A contractual rule does not apply insofar as relying on it would be unacceptable by standards of reasonableness and fairness (Article 6:248(2) DCC); the seriousness of the contractor’s fault is one of the circumstances. A clause in general terms and conditions can be voidable if it is unreasonably onerous (Article 6:233(a) DCC). These general-terms rules do not apply between businesses that are not both established in the Netherlands (Article 6:247(2) DCC); if Dutch law applies, Article 6:248(2) and Article 3:40 DCC remain relevant. Liability for a known hidden defect that the contractor concealed cannot be excluded or limited, and cannot be made subject to shorter limitation periods than Article 7:761 provides (Article 7:762 DCC).
What do you do when your contractor does not show up?
When your contractor stops showing up, ask for an explanation and confirm any new agreements in writing. If the work does not resume, send a written notice of default with a reasonable period to resume (Article 6:82 DCC). If it becomes likely before the delivery date that the work will not be delivered on time, the court can dissolve the contract early (Article 7:756(1) DCC).
A standstill causes frustration and financial damage, such as loss of rent, extra storage costs or longer temporary housing. Construction contracts usually contain a delivery date but often no interim milestones. You do not always have to wait until that date. If it becomes likely before the delivery date that the work will not be delivered on time or properly, the court can dissolve the contract at your request (Article 7:756(1) DCC). If you have good grounds to fear that the contractor will fail to perform, you can ask him in writing, stating those grounds, to confirm within a reasonable period that he will perform; if he does not, the consequences of non-performance arise before the delivery date (Article 6:80(1)(c) DCC).
Preventively, you can agree interim milestones in the contract, for example dates for completing the foundation, the roof structure and the finishing. Concrete dates make it easier to show that the work is behind schedule.
Repeated absence and vague explanations can be a sign of financial problems. Be careful with further payments until the work resumes: you may suspend your payment to the extent the contractor’s failure justifies it (Article 6:262 DCC). Avoid paying in advance for materials that have not been delivered to the site.
Does the contractor miss the delivery date? Then he owes damages for the delay once he is in default. If the contract sets a fixed deadline, default arises when it expires, unless the deadline has a different purpose (Article 6:83(a) DCC). Damages for delay are only owed for the period of default (Article 6:85 DCC). Some contracts contain a penalty for late delivery. A penalty as a rule replaces statutory damages (Article 6:92(2) DCC). At the client’s request, the court can award additional damages if fairness clearly requires it; at the contractor’s request, it can reduce the penalty if fairness clearly requires it, but not below the statutory damages (Article 6:94 DCC). Without a penalty clause, you claim the damage you actually suffered, such as extra rent, storage costs or lost income. Document these costs with contracts, invoices and accounts.
What are your rights if your Dutch contractor goes bankrupt?
If your contractor goes bankrupt, a trustee (curator) takes over the management of the estate. Hold further payments for now and contact the trustee. Ask him in writing, setting a reasonable period, whether he will perform the contract; if the contract has not yet been fully performed by both sides and he does not confirm in time, he as a rule loses the right to demand performance from you (Article 37 Dutch Bankruptcy Act).
The bankruptcy of a contractor has far-reaching consequences. From the day of the bankruptcy order, the contractor loses the right to manage and dispose of the assets in the estate (Article 23 Bankruptcy Act); the trustee manages and liquidates the estate (Article 68(1) Bankruptcy Act). For you as client, this means uncertainty about the completion of the project.
Your own claims against the contractor, for example for defects or extra costs, are as a rule ordinary unsecured claims, which are paid only after creditors with security or priority (Articles 3:277 and 3:278 DCC); recovery is therefore uncertain. If you both owe the contractor money and have a claim against him, set-off may be possible if both arose before the bankruptcy or result from acts carried out with the contractor before it (Article 53 Bankruptcy Act).
You can find the trustee in the Central Insolvency Register (Centraal Insolventieregister) or through the district court that declared the bankruptcy. Send him a letter with the contract details, the status of the work, the payments made and a request to state within a reasonable period whether he will perform. If he declares that he will perform, he must provide security for that performance (Article 37(2) Bankruptcy Act).
If the trustee does not confirm in time, he can as a rule no longer demand performance from you. Discuss with a lawyer whether and how to end the contract before you engage another contractor. Submit your claims, such as the extra costs of a replacement contractor, delay damage or repair costs, to the trustee in writing, stating their nature and amount and enclosing the supporting documents (Article 110 Bankruptcy Act).
Guarantee schemes and insurance can cover part of the risk of bankruptcy or defects; their scope differs per scheme. For the construction of a home for a consumer (contracts concluded on or after 1 January 2024), the contractor must inform the client in writing and unambiguously, before the client is bound, whether and how his performance and his liability for defects are covered by insurance or another financial security (Article 7:765a DCC). Check this before you sign.
How does delivery proceed and what do you do with disputes in the Netherlands?
Delivery (oplevering) takes place when you accept the work, expressly or tacitly (Article 7:758(1) DCC). From then on, the work is at your risk (Article 7:758(2)). The contractor’s liability for defects depends on the rules explained above (Article 7:758(3)-(4) DCC).
In practice, client and contractor inspect the work together and record the result, including any defects and outstanding items, in a written delivery report (proces-verbaal van oplevering) that both sign. The law does not require such a report: delivery follows from acceptance (Article 7:758(1) DCC). For building works under contracts concluded on or after 1 January 2024, the contractor must hand over a file with drawings, calculations, a description of the materials and installations used, and the information needed for use and maintenance, when he announces that the work is ready for delivery (Article 7:757a DCC).
Important: Once the contractor says the work is ready for delivery, you are deemed to have accepted it if you neither accept nor refuse it within a reasonable period (Article 7:758(1) DCC). You may then lose claims for defects you should have discovered, but the contractor stays liable for undiscovered defects in building works under newer contracts (Article 7:758(3)-(4) DCC). Ask a lawyer to review a delivery report first.
Do you discover defects during delivery? Then accept the work only under reservation, or refuse it while indicating the defects (Article 7:758(1) DCC). Document specifically which points are unsatisfactory: cracks in stucco work, incorrect placement of facilities, unfinished detailing, or quality defects. State per point what you expect: remediation, replacement, or price reduction. Set a deadline for remediation that is reasonable for the type of defect.
If you refuse delivery, indicate the defects (Article 7:758(1) DCC). Whether you still owe part of the price at that point depends on the payment terms; you may suspend payment to the extent the failure justifies it (Article 6:262(2) DCC). For a consumer having a home built, the client can only be obliged to make payments that correspond, at least approximately, to the progress of the construction or to the value of the goods transferred to him, although a deposit with a civil-law notary of up to 10% of the contract price, or substitute security, may be stipulated (Article 7:767 DCC), and the client may withhold up to 5% of the contract price from the last instalment(s) and deposit it with a civil-law notary (Article 7:768 DCC; in its current form for contracts concluded on or after 1 January 2024).
When do you go to a disputes committee or a Dutch court?
You can go to a disputes committee or to arbitration if your contract provides for it, and otherwise to the court. The subdistrict court (kantonrechter) in principle hears claims up to EUR 25,000, including interest accrued up to the summons; higher claims go to the district court, where you need a lawyer (Articles 93 and 79 Code of Civil Procedure).
You do not need a lawyer before a disputes committee; check the fees and the maximum claim in the committee’s own rules. Its decision may take the form of binding advice (bindend advies): it binds the parties as an agreement (Article 7:900(2) DCC), but it is not a court judgment, so if the contractor does not comply you may still need a judgment to enforce it. An arbitral award can be enforced in the Netherlands after leave has been granted by the preliminary relief judge (Article 1062 Code of Civil Procedure).
Whether your contractor is affiliated with a disputes committee may appear from his general terms or from the committee’s website. Without such an arrangement, you can go to court, or agree with the contractor on arbitration or binding advice; that requires his consent.
Court proceedings are more formal. Claims up to EUR 25,000 in principle go to the subdistrict court; higher claims go to the civil section of the district court. For 2026, the court fees at the subdistrict court range from EUR 139 to EUR 1,504 for legal entities and from EUR 93 to EUR 753 for natural persons, depending on the amount of the claim (Court Fees in Civil Cases Act, table). Fees at the district court are higher. As a rule, the party that loses is ordered to pay the legal costs; the court can set off the costs if each party loses on some points (Article 237(1) Code of Civil Procedure), but the court sets the amount, and you may still bear part of your own costs.
In urgent situations, for example to prevent further damage, to obtain emergency repairs or to unblock necessary work, you can ask for an interim measure in summary proceedings (kort geding) before the preliminary relief judge of the district court (Article 254(1) Code of Civil Procedure). In cases that belong to the subdistrict court, the subdistrict judge is also competent (Article 254(5)). The decision is provisional.
Mediation is an alternative: an independent mediator helps the parties reach a negotiated solution. This can prevent lengthy proceedings and preserve the business relationship. The costs depend on the mediator and the time involved, and the parties agree who pays them.
What preventive measures prevent disputes with contractors in the Netherlands?
A written construction contract is the starting point. It should describe the work, the materials and their quality, the start and delivery dates, the price and payment terms, additional and reduced work, liability for damage during the work, guarantees after delivery and how disputes are settled.
General terms and conditions require attention. Many contractors use standard terms with substantial obligations or limitations. Read them in advance or have them reviewed. A clause in general terms is voidable if it is unreasonably onerous for the other party, or if that party was not given a reasonable opportunity to take note of the terms (Article 6:233 DCC). A party cannot invoke these grounds if, when the contract was concluded, it was a legal entity that had last published its annual accounts (or to which Article 2:403 DCC applied), if 50 or more persons worked for it, or if it itself repeatedly uses the same or nearly the same general terms (Article 6:235 DCC). For consumers, Articles 6:236 and 6:237 DCC add lists of clauses that are or are presumed to be unreasonably onerous. Between businesses that are not both established in the Netherlands, these rules do not apply (Article 6:247(2) DCC).
Check beforehand whether the contractor is registered in the Trade Register and still active, ask for reference projects and for proof of liability insurance, and check what that insurance covers.
Keep records during the project: photographs of each phase, correspondence, quotations, invoices and changes. Confirm oral agreements in writing by email. These documents help if there is a dispute.
Link interim payments to milestones and avoid large advance payments. Link further payments to concrete progress, for example after the foundation, the roof structure and the finishing, with a final instalment after delivery. For a consumer having a home built, payments are limited by Article 7:767 DCC.
Frequently asked questions about disputes with a Dutch contractor
What does Article 7:759 Dutch Civil Code say about remedying defects?
If the work shows defects after delivery for which the contractor is liable, the client must in principle first give the contractor the opportunity to remedy them within a reasonable period, unless this cannot be required of him. The client can demand repair, unless the costs are out of proportion to the interest in repair (Article 7:759 DCC).
What is the contractor’s duty to warn under Article 7:754?
The contractor must warn the client about errors in the assignment that he knew or should reasonably have known, and about defects in what the client provides (Article 7:754(1) DCC). For building works, the warning must be written and unambiguous (Article 7:754(2)). If he fails to warn, he may bear the consequences (Article 7:760(2)).
What is a construction contract under Article 7:750 Dutch Civil Code?
It is the contract under which the contractor undertakes, outside employment, to create and deliver a work of a material nature for a price in money to be paid by the client (Article 7:750(1) DCC). Examples are building, renovation and installation work.
Can a Dutch contractor charge more than the agreed or estimated price?
For additional work you asked for, only if he warned you in time about the price increase, unless you should have understood it yourself (Article 7:755 DCC). An indicative price may not be exceeded by more than 10% without a timely warning (Article 7:752(2) DCC).
Do you need a notice of default before claiming against a contractor?
Usually yes. The contractor is in default after a written notice with a reasonable period to perform, if he does not perform within that period (Article 6:82(1) DCC). No notice is needed if, for example, a fixed deadline has expired or the contractor has said he will not perform (Article 6:83 DCC).
When do you need a Dutch lawyer in a construction dispute?
As soon as the contractor disputes the defects, stops working or invoices additional work you did not agree to. At that point the notice you send and the deadline you set determine whether you can later claim damages or dissolve the contract. A Dutch lawyer can review that step with you and represent you in the proceedings that follow. For a dispute with a contractor, contact our litigation attorneys at MAAK Advocaten.
Primary sources
- Dutch Civil Code (Burgerlijk Wetboek) Book 7: Articles 7:750, 7:751, 7:752, 7:753, 7:754, 7:755, 7:756, 7:757a, 7:758, 7:759, 7:760, 7:761, 7:762, 7:764, 7:765a, 7:767, 7:768 and 7:900
- Dutch Civil Code Book 6: Articles 6:74, 6:76, 6:80, 6:82, 6:83, 6:85, 6:89, 6:92, 6:94, 6:101, 6:162, 6:214, 6:233, 6:235, 6:236, 6:237, 6:247, 6:248, 6:262, 6:265, 6:267, 6:269, 6:270, 6:271 and 6:272
- Dutch Civil Code Book 3: Articles 3:40, 3:277, 3:278 and 3:296
- Transitional Act new Civil Code (Overgangswet nieuw Burgerlijk Wetboek), Article 218; entry into force of the Quality Assurance for Building Act: Stb. 2023, 113 and Stb. 2024, 19
- Dutch Bankruptcy Act (Faillissementswet): Articles 23, 37, 53, 68 and 110
- Dutch Code of Civil Procedure (Wetboek van Burgerlijke Rechtsvordering): Articles 79, 93, 237, 254 and 1062
- Court Fees in Civil Cases Act (Wet griffierechten burgerlijke zaken), table (2026)
- Supreme Court (Hoge Raad) 28 September 2018, ECLI:NL:HR:2018:1810 (dissolution under Article 6:265)