Published on · Last updated
The UAV 2012 are Dutch standard terms for construction contracts, not legislation. They apply if the contract or the specifications (bestek) declare them applicable, and sit on top of the statutory rules (Article 7:750 ff. Dutch Civil Code). Deadlines run in days: have a UAV contract reviewed by a Dutch lawyer before you sign.
In short
- The UAV set fixed periods in days for inspection, approval and extension requests (§ 8(4), § 9) and apply Dutch law to the contract (§ 2(3)).
- Changes are settled as additional or omitted work; the contractor can claim a higher price only if it warned the client in time (§ 36(1a)).
- Since the 2025 version, § 12(4) refers to statutory liability after completion; claims are barred after five years, or ten for collapse or unfitness.
- Disputes go to arbitration unless the specifications say otherwise (§ 49); have the contract checked before signing and when a dispute looms.
This page explains the main UAV clauses on completion, defects, additional work, delay and disputes, based on the current text, the UAV 2012 (versie 2025) published in Staatscourant 2025, 6896. It is written for businesses on either side of the contract that are used to other standard terms at home.
What are the UAV 2012 and when do they apply?
The UAV 2012 (Uniforme Administratieve Voorwaarden voor de uitvoering van werken en van technische installatiewerken 2012) are not legislation but algemene voorwaarden (general terms and conditions). As a rule, they bind the parties because the contract refers to them, in the version the contract names.
The current version, the UAV 2012 (versie 2025), was adopted by the Dutch Minister of Housing and Spatial Planning on 17 February 2025 and published in Staatscourant 2025, 6896. The official text is in Dutch. The 2012 decree on wetten.overheid.nl carries the status note materieel uitgewerkt (materially exhausted) as of 1 April 2025; the UAV are model terms, so what matters is the version your contract names. Under § 2(1), its provisions apply unless the specifications expressly deviate from them. § 2(3) makes Dutch law applicable to the contract.
For a foreign company, signing a contract under the UAV 2012 therefore also means accepting Dutch law. State the full title and the version in the contract. Where the parties are not both established in the Netherlands, the special Dutch rules on general terms (Articles 6:231-6:247) do not apply (Article 6:247(2) and (3) Dutch Civil Code); whether the UAV became part of the contract then follows from offer and acceptance (Article 6:217). More on incorporation in our article on when general terms and conditions apply, and on the wider framework on our main page on construction contracts in the Netherlands. The statutory rules on contracting agreements are covered in contracting agreements in the Netherlands.
What is the difference between the UAV 2012 and the UAV-GC?
The UAV 2012 suit traditional contracting, where the client supplies the design and the specifications and the contractor builds. For design-and-build contracts, in which the contractor also designs, a separate set of terms, the UAV-GC, exists.
That split is visible in § 5(2) UAV 2012: the client is responsible for the structures and working methods it prescribes, including the effect of soil conditions, and for its orders and instructions. The contractor still has a duty of its own. If those structures, methods or instructions obviously contain errors, and building without pointing this out would be contrary to reasonableness and fairness, the contractor is liable for the harmful consequences (§ 6(14)).
The Dutch Civil Code contains a similar duty to warn: the contractor must warn of errors in the assignment it knew or should reasonably have known of (Article 7:754(1)). For a building, paragraph 2 requires the warning to be in writing, unambiguous and timely, and to point out the possible consequences.
How do inspection and completion work under the UAV 2012?
Under the UAV 2012, the work counts as completed on the day the client’s supervisor (the directie) approves it after inspection, or is deemed to have approved it (§ 10(1)). If the contractor never requests an inspection, the client can notify it in writing that it considers the work finished; the fifth day after that notice then counts as completion (§ 10(2)). If no written decision is sent within eight days of the inspection, the work is deemed approved on the eighth day (§ 9(5)).
The process starts with a written request from the contractor stating the day on which it considers the work finished; the supervisor may accept an oral notice recorded in the site diary (§ 9(1)). The inspection takes place as soon as possible and as a rule within eight days of that day (§ 9(2)). If it has not happened within fifteen days, the contractor can send a new request by registered letter; if the supervisor does not inspect within eight days, the work is deemed approved on the eighth day after that letter was sent (§ 9(6)).
Minor defects that can be repaired before the next payment instalment are no ground for refusing approval, provided they do not prevent the work from being used; the contractor must repair them as soon as possible (§ 9(7)). The Civil Code is less precise: Article 7:758(1) refers only to a “reasonable period” for the client to inspect. The UAV replace that open standard with fixed days.
What is the maintenance period under the UAV 2012?
The maintenance period (onderhoudstermijn) is a period after completion during which the contractor repairs, at its own cost, defects that appear. It exists only if the specifications prescribe it; the UAV 2012 do not set a default length (§ 11(1)).
Excluded are defects for which the client is responsible or liable under § 5, defects caused by incorrect or careless use and normal wear and tear (§ 11(2)). At the end, the supervisor inspects the work again (§ 11(6)). If there is a maintenance period, the liability periods in § 12 start only after it ends (§ 12(5)).
How long is the contractor liable for hidden defects?
Under the UAV 2012 (versie 2025), a claim for a defect for which the contractor is liable by law is inadmissible if brought more than five years after completion. The period is ten years where the work has collapsed or threatens to collapse, or has become or threatens to become unfit for its intended purpose, and only very costly measures can fix or prevent this (§ 12(4)).
The five-year period is shorter than the statutory outer limit. Under Article 7:761(2) Dutch Civil Code, a claim for a defect in a building becomes time-barred at the latest twenty years after completion. Within that limit, the claim becomes time-barred two years after the client has complained about the defect or, if the client set a period for repair, two years after that period ends (Article 7:761(1)); the period can be extended while the contractor investigates or repairs the defect (Article 7:761(3)). More on Dutch time limits is in limitation periods in the Netherlands.
The 2025 version also changed the basis of liability. Under the original 2012 text of § 12, the contractor was in principle no longer liable after completion, except for defects attributable to it that the supervisor could not have detected despite careful supervision and that were reported within a reasonable time after discovery. Those paragraphs were deleted in 2025; § 12(4) now refers to liability “krachtens de wet“, meaning by law.
That statutory rule is Article 7:758(4): for buildings, the contractor is liable for defects not discovered at completion, unless they cannot be attributed to it. Other clients can accept a deviation only if the contract expressly says so; a consumer cannot. Paragraph 4 does not apply to contracts concluded before the Quality Assurance for Building Act took effect on 1 January 2024 (Article 218(1) Transitional Act new Civil Code). Liability for a known defect that the contractor concealed cannot be excluded, limited or made subject to shorter periods (Article 7:762).
Important: If your contract refers to the original 2012 text, or deviates from Article 7:758(4), the liability regime is not the one the 2025 text assumes. Check which version applies and whether any deviation is expressly stated in the contract, and have a Dutch contract lawyer review it before a defect becomes a dispute.
Not sure which liability regime applies to your project? Our contract lawyers can review the construction contract with you.
How is additional work paid under the UAV 2012?
Additional and omitted work is settled under the UAV 2012 for changes to the specifications, the work or the conditions of execution, and also for deviations in provisional sums and quantities (§ 35(1), § 36(1)). For changes the client wants, the contractor can claim a higher price only if it warned the client in time that the change would increase the price (§ 36(1a)).
This mirrors Article 7:755 Dutch Civil Code, with the same exception: no warning is needed if the client should have understood the need for a price increase on its own. The parties agree the price of a change before it is carried out or, if that is not possible, as soon as possible (§ 36(4)).
The UAV also set limits. The contractor must carry out changes as long as the additions and the deductions each stay within 15% of the contract sum, or their balance within 10% (§ 36(3)). If a dispute has already started, read our article on a legal dispute over additional work with a contractor.
When does a contractor get an extension of time?
A contractor is entitled to an extension of time if, because of force majeure, circumstances at the client’s risk, or changes to the specifications or the execution, it cannot be required to complete within the agreed period (§ 8(5)). The request should be made in writing and in time (§ 8(4)).
Under § 8(4), a request is considered only if it is in writing and reaches the supervisor at least fourteen days before the completion period expires, unless the supervisor waives this. The fourteen days count back from the completion date, not forward from the moment the delay starts.
What does late completion cost under the UAV 2012?
For late completion, the client can impose a deduction (korting) on the contract sum. The amount is set in the specifications; if they are silent, the deduction is € 60 per day (§ 42(2)).
The deduction is due as soon as the completion date passes, without any notice of default (§ 42(5)). No deduction applies for days after the completion period that are not working days, or for delay caused by force majeure that has not already been reflected in an extension (§ 42(3)). As a rule, such a deduction is a boetebeding (penalty clause) within the meaning of Article 6:91 Dutch Civil Code. A court can reduce it at the contractor’s request if fairness clearly requires this, but not below the damages due by law (Article 6:94(1)).
Example: a design change and a missed completion date
Suppose (illustration) a German contractor builds a warehouse for a Dutch logistics company, with the UAV 2012 (versie 2025) declared applicable and a completion date in the specifications. Halfway through, the client wants an extra loading dock. The supervisor approves the change verbally at a site meeting; the minutes only say “extra dock agreed”.
The contractor builds the dock and completes two weeks late. It never requested an extension in writing and never warned that the change would cost more. The client deducts the penalty and refuses the invoice for the additional work.
The change can give a right to an extension (§ 8(5)), and even without a written instruction both parties keep their right to have the change settled (§ 36(5)). On the other hand, the contractor did not request the extension in time (§ 8(4)) and did not announce the price increase (§ 36(1a)). For the extra price, the outcome turns on whether the client should have understood that an extra loading dock costs money.
Does an arbitrator or a court decide a UAV dispute?
The UAV 2012 refer disputes by default to arbitration (arbitrage) under the arbitration rules of the Raad van Arbitrage voor de Bouw as they read three months before the tender date (§ 49(2)). The parties thereby waive the ordinary courts (§ 49(1)), unless the specifications expressly provide otherwise (§ 2(1)).
Important: Under § 49(3), once the client has communicated its final decision on the final account in writing and has pointed out the six-month period by registered letter, the contractor can no longer claim more than the final account if it starts proceedings later, unless the claim arises from a circumstance that only became apparent after that period. Have a Dutch lawyer check the dates.
Check the dispute clause in the specifications and the contract first; the UAV are only the starting point. During a dispute, the contractor must continue the work if the supervisor asks, unless the arbitration board decides otherwise in urgent proceedings (§ 50(1)). How construction arbitration works is explained in conducting a construction dispute through arbitration. If you are considering ending the contract instead, see terminating a construction contract under Dutch law.
When should you have a UAV construction contract reviewed?
Have a UAV construction contract reviewed before you tender or sign, and again as soon as a change, delay or defect starts to cost money. Many UAV deadlines run in days, such as the eight days in § 9 and the fourteen days in § 8. Check in particular:
- Which version of the UAV 2012 applies, and where the specifications deviate from it.
- Whether the specifications prescribe a maintenance period, and for how long.
- The amount of the deduction for late completion.
- How changes and price agreements are recorded in writing.
- Who decides disputes: the arbitration board or the ordinary courts.
Are you about to sign a construction contract under the UAV 2012, or is there already a disagreement about completion, additional work or a deduction? Our contract lawyers can assess your position before a deadline passes. Read more about the construction lawyer in the Netherlands page.
Frequently asked questions about the UAV 2012
Are the UAV 2012 mandatory for construction contracts in the Netherlands?
No. The UAV 2012 are standard terms and apply only if the contract or specifications declare them applicable. Without that reference, the statutory rules on construction contracts in Article 7:750 and following of the Dutch Civil Code apply.
Does Dutch law apply if my contract refers to the UAV 2012?
Yes, as a rule. § 2(3) UAV 2012 makes Dutch law applicable to the contract. A foreign company that signs a contract under the UAV 2012 therefore accepts Dutch law, including the Dutch rules on construction contracts, unless the specifications expressly deviate (§ 2(1)).
What is the UAV 2012 (versie 2025)?
It is the revised text adopted by the Dutch Minister of Housing and Spatial Planning on 17 February 2025 and published in Staatscourant 2025, 6896. The main change concerns § 12: the old rule that the contractor was in principle no longer liable after completion was deleted, so liability now follows the law.
Within what period must the client pay?
Under § 40(6), an instalment must be paid within four weeks after the inspection has shown that the contractor is entitled to it. If the specifications require an invoice, the four weeks run from the moment the invoice is properly received by the supervisor.
Can the client demand a bank guarantee under the UAV 2012?
Yes, if the client has stipulated one: a bank guarantee of 5% of the contract sum, unless the specifications provide otherwise (§ 43a(1)-(3)). It cannot be stipulated if part of the contract sum is withheld (§ 43a(7)). The contractor can demand security if the client does not pay or is unlikely to pay on time (§ 43a(8)).
Primary sources
Dutch statutes are only officially available in Dutch, on wetten.overheid.nl. The UAV 2012 are published in the Staatscourant.
- UAV 2012 (versie 2025), Staatscourant 2025, 6896: § 2, 5, 6, 8, 9, 11, 12, 35, 36, 40, 42, 43a, 49 and 50, and the explanatory note on § 12
- UAV 2012, original 2012 text (Staatscourant 2012, 1567): § 12
- Dutch Civil Code (Burgerlijk Wetboek) Book 6: Article 6:91, Article 6:94, Article 6:217 and Article 6:247
- Dutch Civil Code Book 7: Article 7:750, Article 7:754, Article 7:755, Article 7:758, Article 7:761 and Article 7:762
- Transitional Act new Civil Code (Overgangswet nieuw Burgerlijk Wetboek): Article 218