Terminating a Construction Contract under Dutch law

Published on · Last updated

Under Dutch law, a client can end a construction contract by cancellation (opzegging) or dissolution (ontbinding). Cancellation is possible at any time, but the client pays the price for the whole work minus the contractor’s savings (Article 7:764 Dutch Civil Code). Dissolution requires a failure in performance and, as a rule, default (Article 6:265). The unperformed part need not be paid.

The construction sector regularly faces time pressure, staff shortages and planning complications. Contractors falling behind schedule due to excessive simultaneous projects, clients failing to meet payment deadlines, or quality problems escalating – these situations force parties into difficult decisions. Termination of the construction contract represents a legal crossroads with potentially far-reaching financial consequences.

Specific statutory rules on the contract for work (aanneming van werk) in Title 12 of Book 7 Dutch Civil Code govern construction contracts (Article 7:750 and following). Additionally, standard conditions such as UAV 2012, AVA 2013 or AVV 1998 frequently apply. These conditions sometimes deviate from statutory law, requiring extra attention during termination. Wrong choices often lead to costly legal proceedings.

What Does Dissolution of Construction Contracts Mean Under Dutch Law?

You can dissolve a construction contract, wholly or partly, if the other party fails to perform one of its obligations, unless the failure, given its special nature or minor significance, does not justify dissolution. As a rule, the debtor must be in default, unless performance is permanently or temporarily impossible (Article 6:265(1) and (2) Dutch Civil Code). You dissolve by written declaration or through the court (Article 6:267).

Article 6:265 Dutch Civil Code is the general statutory basis for dissolution of reciprocal agreements. It is default law, so the contract or the applicable standard conditions may contain other rules. For construction contracts, Article 7:756 Dutch Civil Code additionally applies. Under this provision, the court can dissolve the agreement in whole or in part at the client’s request if, even before the agreed delivery date, it becomes likely that the work will not be delivered on time or properly. The court determines the consequences of the dissolution and may attach conditions to it (Article 7:756(3)).

This expanded dissolution possibility contains an important condition: only the court can pronounce this dissolution. Extrajudicial dissolution under Article 6:265 Dutch Civil Code remains possible, but requires a written declaration (Article 6:267(1)) and, as a rule, that the contractor is in default. You can also ask the court to dissolve the contract under Article 6:265 (Article 6:267(2)).

Which Conditions Apply for Valid Dissolution in the Netherlands?

Dissolution first requires a failure in performance (tekortkoming). The failure does not have to be attributable to the other party: dissolution is also possible in a case of force majeure. Attributability does matter for damages (Article 6:74(1) Dutch Civil Code). Dissolution is excluded only if the failure, given its special nature or minor significance, does not justify dissolution with its consequences (Article 6:265(1)). Minor defects or marginal delays will therefore often not suffice.

Moreover, the debtor must as a rule be in default (verzuim). Usually this means you give the other party formal written notice (ingebrekestelling) with a reasonable period for performance. Default arises if performance does not follow within that period (Article 6:82(1) Dutch Civil Code). The law sets no fixed number of days; what is reasonable depends on the nature and scope of the failure and the urgency.

Exceptions: if performance is permanently or temporarily impossible, dissolution does not require default at all (Article 6:265(2)). Default arises without notice if an agreed deadline for performance passes, unless the deadline has a different purpose, or if you must infer from a statement of the debtor that it will fail to perform, for example an unambiguous refusal to continue the work (Article 6:83 Dutch Civil Code). If the debtor is temporarily unable to perform, or if its attitude shows that a notice would be useless, a written statement holding it liable suffices (Article 6:82(2)).

How Does Financial Settlement Work After Dissolution According to Dutch Legislation?

Dissolution has no retroactive effect (Article 6:269 Dutch Civil Code). Parties are released from obligations not yet performed. For performances already rendered, an obligation to undo them arises (Article 6:271). Dissolution can also be partial; it then reduces the mutual performances proportionally (Article 6:270).

In theory, this means the contractor returns paid instalments and the client returns the work and installed materials. With partially completed construction work, that is usually impossible. If the nature of the performance excludes undoing it, compensation for its value at the time of receipt takes its place. If the work did not meet the contract, that compensation is limited to the value it actually had for the client in the circumstances (Article 6:272(1) and (2) Dutch Civil Code).

A fictitious example: a client dissolves the agreement after the contractor has completed part of a renovation project. The contract price is €200,000 and the client has already paid €120,000. Suppose the value of the work performed, taking the defects into account, is €105,000. The contractor must then repay €15,000 (€120,000 paid minus €105,000 value).

Additionally, if the failure is attributable to the contractor, the client is entitled to damages for the loss caused by dissolution instead of mutual performance (Article 6:277 Dutch Civil Code). These damages can include additional costs for completion by third parties, expert costs and consequential damages such as rental loss or delay damages.

When Can You Cancel a Construction Contract in the Netherlands?

Cancellation by the client is possible at any time, wholly or partly, without stating reasons (Article 7:764(1) Dutch Civil Code). The client then pays the price for the whole work, reduced by the savings that result for the contractor from the cancellation, against delivery of the work already completed (Article 7:764(2)). Savings are the costs the contractor no longer has to incur because of the cancellation.

Article 7:764 paragraph 1 Dutch Civil Code grants the client this special power. Cancellation requires no notice of default, no court and no failure by the contractor.

Unless the contract or the applicable conditions require a specific form, cancellation can be made in writing, orally or even implicitly through conduct (Article 3:37(1) Dutch Civil Code). It takes effect once it has reached the contractor (Article 3:37(3)). Written cancellation is strongly preferable for evidence. A bailiff can serve the cancellation, which gives you strong proof of its content and date.

Paragraph 14 UAV 2012 contains a comparable arrangement: the client may instruct the contractor to end the work in an incomplete state (beëindiging in onvoltooide staat, § 14(7) UAV 2012). If AVA 2013, AVV 1998 or other conditions apply, check their own termination provisions.

What Financial Obligations Arise Upon Cancellation Under Dutch Law?

Article 7:764 paragraph 2 Dutch Civil Code provides that the client must pay the price for the whole work, reduced by the savings that result from the cancellation, against delivery of the work already completed. If the price depended on the costs the contractor would actually incur, the price owed is calculated on the basis of the costs incurred, the work performed and the profit the contractor would have made on the whole work.

Costs already incurred are not savings. Has the contractor bought materials it cannot return or use elsewhere? Then their cost is not saved. The same can apply to staff and subcontractors with commitments the contractor cannot cancel.

The amount of the savings is often disputed. The contractor knows its own costs best. Ask the contractor for a substantiated statement of what it has already spent, which commitments it still has and what it saves because of the cancellation.

In practice, cancellation can be expensive even early in the project, because only the costs the contractor actually saves are deducted. Materials may already be ordered, staff scheduled and subcontractors contracted.

A fictitious calculation: the contract price is €300,000 and the work is 30% complete when the client cancels. The contractor’s savings from the cancellation amount to €90,000. The client then pays €210,000 (€300,000 minus €90,000), although only 30% of the work has been realised.

How Do You Determine the Correct Termination Method in the Dutch Jurisdiction?

Dissolution generally costs the client less than cancellation, because in principle only the value of the work performed is paid, not the price for the whole work. However, dissolution requires a failure in performance and, as a rule, default. If it turns out that you were not entitled to dissolve, your declaration may be construed as a cancellation, with the financial consequences of Article 7:764 Dutch Civil Code.

This risk is real. If a client relies on dissolution, but the court or arbitrators find that there was no failure or no default, the termination declaration may be treated as a cancellation under Article 7:764 Dutch Civil Code. Whether that happens depends on what you wrote and how the contractor could reasonably understand it.

Communication plays a central role. An email where the client writes “we’re pulling the plug” can legally be construed as cancellation, even if the sender intended dissolution. Formulation determines legal qualification and thereby financial consequences.

Therefore it merits recommendation to:

  1. Use exact legal terminology in termination declarations
  2. Explicitly mention whether you dissolve or cancel
  3. For dissolution, specify the breach in detail
  4. Refer to previous notices of default with dates and deadlines
  5. Have a lawyer draft the termination declaration beforehand

Which Strategic Considerations Are Relevant Under Dutch Law?

Timing is an essential factor. If the work is suspended for a long time because of circumstances in the client’s risk sphere (objection procedures, contamination, archaeological finds), cancellation can be more advantageous than continuation. The contractor may then claim damages for the standstill. Under UAV 2012, the contractor is compensated for damage caused by a suspension, and may end the work in an incomplete state if the suspension of the whole work lasts longer than six months (§ 14(4) and (6) UAV 2012).

A fictitious example: the work is suspended for six months due to permit problems, and the contractor claims €80,000 in standstill damages. If you cancel, you pay the price for the whole work minus the contractor’s savings. Calculate both scenarios before you choose: on cancellation you also pay for what has already been built, but the standstill damage stops growing.

Documentation of work status proves essential during termination. Have the work status recorded independently, preferably by the Arbitration Board or through a bailiff who creates an official observation report. This recording determines the basis for financial settlement in both dissolution and cancellation.

What Are the Consequences of Termination for Payment Schedules in the Netherlands?

After dissolution, payment schedules lose their meaning as a payment plan, because the obligations end for the future. What the contractor receives for the work performed follows from its value (Article 6:272 Dutch Civil Code), not from a pro rata application of the agreed instalments. Additional costs for completion by a third party fall under damages (Article 6:277).

Payment schedules base themselves on the starting point of complete execution. With termination through dissolution, however, primarily the additional costs and client damages prove relevant – consider expert costs for quality assessment, additional costs for engaging a new contractor, and potential consequential damages.

How Does Work Inspection Relate to Termination According to Dutch Legislation?

Before having the work completed by a third party, a thorough inspection is necessary. This applies more strongly to dissolution than to cancellation, but is valuable in both cases.

This investment prevents discussions about:

  • Exact completion percentage at moment of termination
  • Quality of executed work
  • Present materials and building supplies
  • Potential defects or shortcomings
  • Necessary remedial work

With changed scope or non-completion, this inspection determines the amount of compensation due to the contractor. Without a documented inspection, evidentiary problems arise that can considerably delay proceedings.

What Role Do Standard Conditions Play in Termination Under Dutch Law?

Standard conditions can contain their own termination rules. Paragraph 14 UAV 2012, for example, governs the termination of the work in an incomplete state: the contractor is then entitled to the contract sum, increased by the costs it had to incur because the work was not completed and reduced by the costs saved by the termination (§ 14(10) UAV 2012).

This arrangement closely resembles Article 7:764(2) Dutch Civil Code: the calculation also starts from the price for the whole work. A difference is that UAV 2012 expressly adds the costs of non-completion to the contract sum. Under UAV 2012 the contractor may also end the work in an incomplete state in some cases, for example if the suspension of the whole work lasts longer than six months, or if circumstances for the client’s account have delayed the work for more than two months without interruption (§ 14(6) and (8) UAV 2012).

Article 7:764 Dutch Civil Code is not among the provisions the law declares mandatory, so parties can agree on a different compensation arrangement in their contract. Always read the conditions that apply to your contract first. For the construction of a home for a consumer, additional rules apply from which no deviation is possible to the consumer’s detriment, except in a standard arrangement as referred to in Article 6:214 (Article 7:765 and 7:769 Dutch Civil Code). For example, the consumer may in principle dissolve the contract within three days after receiving the written contract (Article 7:766(2)). That does not apply if the home is built on land the consumer already owns and the contract is not connected with the purchase of that land (Article 7:766(3)).

Why Does Termination Under Standard Conditions Require Extra Attention in the Netherlands?

Standard conditions can prescribe deadlines and formalities in addition to those of the Dutch Civil Code. Under § 46(1) UAV 2012, the client gives the contractor written notice of default with a reasonable period, as under Article 6:82 Dutch Civil Code. If the contractor remains in default, the client may complete the work, or have it completed, at the contractor’s expense; in urgent cases the client may take measures earlier. Complying with these rules is important for a valid termination.

Moreover, standard conditions often provide for arbitration. Under § 49 UAV 2012, disputes are settled by arbitration under the arbitration rules of the Raad van Arbitrage voor de Bouw (now the Raad van Arbitrage in bouwgeschillen), not by the ordinary courts. If you nevertheless start proceedings on the merits in court, the court declares that it has no jurisdiction if the other party invokes the arbitration agreement before any other defence, unless the agreement is invalid (Article 1022 Dutch Code of Civil Procedure). Summary proceedings before the preliminary relief judge remain possible (Article 1022a).

Therefore pay attention during contract conclusion to:

  • Which standard conditions are declared applicable
  • Whether deviating termination arrangements are included
  • Which dispute resolution applies
  • Whether specific deadlines or formalities apply
  • How compensation calculation is arranged upon termination

How Do You Prevent a Stalemate During Termination in the Dutch Jurisdiction?

A stalemate arises when your declaration qualifies neither as dissolution nor as cancellation: there was no failure or no default, and you did not clearly cancel either. The contract then simply continues. The contractor can claim performance, and you can still cancel, with the consequences of Article 7:764 Dutch Civil Code.

An example shows the risk. A client sends an email saying “we’re pulling the plug”, followed by a letter from its lawyer about partial dissolution. If the court finds that there was no failure at that moment, but also no clear cancellation, the dissolution has no effect and no cancellation has taken place either.

The result can be that both parties come away empty-handed in those proceedings: the contractor obtains no contract price on the basis of cancellation, and the client obtains no recognised dissolution. Such an impasse can lead to lengthy proceedings.

Which Best Practices Minimize Termination Risks in the Netherlands?

Early legal advice remains the most important protection. Have a specialized lawyer analyze the situation before taking termination steps. This analysis includes:

  1. Assessment whether dissolution is possible based on documented breaches
  2. Verification whether correct notice of default occurred
  3. Estimation of financial consequences with dissolution versus cancellation
  4. Formulation of legally watertight termination declaration
  5. Preparation of work inspection and evidence collection

Solid documentation during execution prevents evidentiary problems afterwards. Record breaches through emails, photographs, independent expert reports and written warnings. This documentation supports dissolution and weakens the counterparty’s defense.

Do you need certainty about your legal position with a problematic construction contract? Our specialized lawyers in Amsterdam analyze your specific situation and advise on the optimal termination strategy, considering financial consequences and procedural risks.

Which Specific Situations Demand Termination Under Dutch Law?

Prolonged stagnation, quality defects making repair impossible, and payment problems constitute the most common reasons for terminating construction contracts. Each scenario demands a specific legal approach aligned with factual circumstances and contractual context.

How Do You Terminate Upon Repeated Breaches in the Netherlands?

Repeated minor breaches can collectively constitute dissolution grounds, even though each individual breach alone does not justify dissolution. Consider a contractor who structurally:

  • Arrives 30 minutes to one hour later than agreed
  • Delivers materials of lesser quality than specified
  • Neglects cleanup work
  • Fails to communicate about progress

Cumulatively, these behaviors can indicate lack of professionalism and commitment. Document each breach separately and upon continuation always send written warnings. This pattern formation supports a subsequent dissolution request.

When Does Cancellation Prevail Over Continuation According to Dutch Legislation?

With risks in the client’s sphere, cancellation can prove strategically advantageous. For example with permit problems causing suspension of six months or longer. The contractor accumulates stagnation damage for standstill of personnel, equipment and subcontractors.

Do the calculation: if standstill damage keeps growing every month, cancellation can limit the total cost, even though on cancellation you pay the price for the whole work minus the contractor’s savings (Article 7:764(2) Dutch Civil Code). Strategic cancellation then works as a way to limit further damage.

With fundamental changes of scope during execution, too, cancellation, possibly partial (Article 7:764(1) Dutch Civil Code), can be preferable to amending the contract. A new contractor can then carry out the changed work without inheriting the old planning and agreements.

What Are Common Mistakes During Termination in the Netherlands?

The biggest mistake during termination is unclear communication about the chosen legal ground. A second mistake is insufficient documentation of the failures and the default, so that dissolution cannot be substantiated afterwards. Both mistakes can lead to your declaration being construed as a cancellation, with costly financial consequences.

Why Do Dissolutions Fail in Practice Under Dutch Law?

Premature dissolution without a correct notice of default is the main pitfall. As a rule, you must give the contractor a reasonable period in writing to perform after all (Article 6:82(1) Dutch Civil Code). The law sets no fixed number of days. What is reasonable depends on the circumstances, such as the nature of the defect and the urgency; with acute safety risks, a short period can be reasonable.

Without a notice of default, no default arises and the dissolution fails, except where default arises without notice (Article 6:83 Dutch Civil Code), where a written statement holding the contractor liable suffices (Article 6:82(2)), or where performance is permanently or temporarily impossible (Article 6:265(2)). Your termination declaration may then be construed as a cancellation, with the financial consequences of Article 7:764. Follow the requirements carefully.

Insufficient specification of the breach forms a second problem. A general complaint like “you work too slowly” or “the quality is inadequate” does not suffice. Specify exactly:

  • Which contractual obligation was violated
  • On which dates and times the breach occurred
  • Wherein the breach consists (deviation from specification, deadline overrun, etc.)
  • Which damage or disadvantage results
  • Which remedy within which deadline is demanded

Which Communication Errors Lead to Disputes in the Netherlands?

Mixed signals between parties cloud legal qualification. For example: first announcing dissolution, then nevertheless entering into negotiation about amicable termination, subsequently communicating cancellation. This inconsistency makes unclear afterwards which termination ground parties envisioned.

Cancelling orally is possible but without written confirmation it creates evidentiary problems. Extrajudicial dissolution must be made in writing, or electronically if the contract was concluded electronically (Article 6:267(1) Dutch Civil Code). The other party can dispute that the contract was terminated, or the date. Without proof of termination, it is uncertain when the contractual obligations ended.

Therefore send your declaration by registered mail with acknowledgment of receipt and by email, or have a bailiff serve it. A declaration only takes effect once it has reached the addressee (Article 3:37(3) Dutch Civil Code). This formality may seem excessive, but it prevents months of discussion about whether and when termination occurred.

Frequently asked questions about terminating a construction contract under Dutch law

What does Article 7:764 of the Dutch Civil Code say?

In an unofficial translation: “1. The client is at all times entitled to terminate the contract in whole or in part. 2. In the event of such termination, he must pay the price applicable to the whole work, reduced by the savings resulting for the contractor from the termination, against delivery by the contractor of the work already completed. If the price was made dependent on the costs actually to be incurred by the contractor, the price owed by the client is calculated on the basis of the costs incurred, the work performed and the profit the contractor would have made on the whole work.” The binding Dutch text is on wetten.overheid.nl.

What does Article 6:265 of the Dutch Civil Code say about termination for non-performance?

In an unofficial translation: “1. Every failure of a party to perform one of its obligations entitles the other party to dissolve the contract in whole or in part, unless the failure, given its special nature or minor significance, does not justify dissolution with its consequences. 2. To the extent that performance is not permanently or temporarily impossible, the right to dissolve only arises when the debtor is in default.” Paragraph 2 therefore usually requires a notice of default first (Article 6:82). The binding Dutch text is on wetten.overheid.nl.

Can a contractor terminate a construction contract in the Netherlands?

Not by cancellation: Article 7:764 Dutch Civil Code gives that right only to the client. The contractor can dissolve the contract if the client fails to perform, as a rule after default (Article 6:265), or ask the court to dissolve it if, even before delivery, it becomes likely that the client will not perform properly (Article 7:756(2)). Under UAV 2012, the contractor may end the work in an incomplete state if the suspension of the whole work lasts longer than six months (§ 14(6) UAV 2012).

Can a client cancel a building project after a death in the family?

Yes. The client can cancel at any time, wholly or partly, without giving reasons, but must then pay the price for the whole work minus the contractor’s savings (Article 7:764 Dutch Civil Code). A death in the client’s family does not change that calculation. The law gives a separate termination right only if the contractor dies or becomes permanently unfit for work (Article 7:763). A consumer who has a home built may also have a three-day cooling-off period after receiving the written contract (Article 7:766(2)).

What happens to work already built after dissolution of a construction contract?

Dissolution has no retroactive effect (Article 6:269 Dutch Civil Code). For what has already been performed, an obligation to undo it arises (Article 6:271). If partly built work cannot be returned, the client pays its value instead; if the work did not meet the contract, that is the value it actually had for the client (Article 6:272). Damages are owed only if the failure is attributable, with a limited exception (Article 6:277).

Primary sources

Need advice on terminating a construction contract in the Netherlands?

Contact our law firm in Amsterdam for personal legal advice about terminating your construction contract. Our specialists assess your situation, calculate financial scenarios and guide the termination process from A to Z.

News & Insights
Which topics would you like to receive updates on?
Who Are You?
Which industry or sector do you operate in? (Optional)